Technical Assistance for Financing Framework for Rogun Hydropower Project

Resumen*

The Project will support the following components: Component 1: Development of a macroeconomically sustainable financing plan and a commercial framework for Rogun HPP Project. This component will finance: (a) revision of the Rogun HPP Project construction completion schedule taking into account the existing and projected macro-fiscal framework of the country; (b) preparation of the Rogun HPP Project financing plan taking into account the updated...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

The project development objectives are to strengthen Rogun HPP Project’s financial and commercial frameworks, enhance its environmental and social sustainability, improve the transparency, and support establishment of Rogun HPP Project’s benefit sharing program

Llave Detalles

Proyecto Detalles

  • P178819

  • Active

  • Christopher Trimble , Manuel Berlengiero

  • Republic of Tajikistan

  • Tayikistán

  • 28 de mayo de 2022

  • (a partir de la presentación ante el Directorio)

    12 de enero de 2023

  • 11 de mayo de 2023

  • US$ 20.00 millones

  • Project Management Group for Energy Facilities Construction

  • Europa y Asia central

  • 2023

  • US$ 20.00 millones

  • N/A

  • 8 de mayo de 2024

  • 31 de diciembre de 2026

  • Yes

  • BANK APPROVED

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
Asian Infrastructure Investment Bank 5.00
IDA Grant 15.00

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF No Disponible
Compromiso de la AIF 15.00
Compromiso del BIRF + AIF 15.00
Instrumento de Financiamiento
Monto a título de donación 5.00
Costo total del proyecto** 20.00

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Project Management Moderately Satisfactory 2024-11-12
Overall Implementation Progress (IP) Satisfactory 2024-11-12
Progress towards achievement of PDO Satisfactory 2024-11-12
Monitoring and Evaluation Satisfactory 2024-11-12
Procurement Satisfactory 2024-11-12
Financial Management Moderately Satisfactory 2024-11-12

CALIFICACIONES DE LA TERMINACIÓN

No hay datos disponibles.

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

No hay datos disponibles.

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • The Government adopts a macroeconomically sustainable and financially viable plan for completing construction of Rogun HPP ProjectValorNoNoYes
    Fecha31 de octubre de 202223 de abril de 202431 de diciembre de 2023
    Comentar
  • Rogun HPP Project has functioning dam safety as well as environmental and social POEsValorNoYesYes
    Fecha31 de octubre de 202217 de octubre de 202328 de febrero de 2023
    Comentar
  • The summary information on existing and future contracts and financing plan for completion of construction of Rogun HPP Project arepublicly disclosedValorNoYesYes
    Fecha31 de octubre de 202223 de abril de 202431 de marzo de 2023
    Comentar
  • PPAs are signed for sale of Rogun HPP Project’s electricity in the amount to make the financing plan viableValorNoNoYes
    Fecha31 de octubre de 202223 de abril de 202431 de diciembre de 2023
    Comentar
  • The environmental and social instruments of Rogun HPP Project comply with the requirements of the World Bank’s Environmental and Social FrameworkValorNoYesYes
    Fecha31 de octubre de 202223 de abril de 202428 de febrero de 2024
    Comentar
  • Rogun HPP Project’s community benefit sharing program is launchedValorNoNoYes
    Fecha31 de octubre de 202223 de abril de 202430 de abril de 2024
    Comentar

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Rogun PMG is strengthened with project management, procurement, FM, and E&S expertsValorNoYesYes
    Fecha31 de octubre de 202224 de abril de 20241 de febrero de 2023
    Comentar
  • Update of Rogun HPP Project implementation schedule is completedValorNoNoYes
    Fecha31 de octubre de 202223 de abril de 202431 de enero de 2023
    Comentar
  • Dam safety POE, with composition and qualifications acceptable to the Bank, is hiredValorNoYesYes
    Fecha31 de octubre de 202223 de abril de 202431 de enero de 2023
    Comentar
  • E&S POE, with composition and qualifications acceptable to the Bank, is hired and retainedValorNoYesYes
    Fecha31 de octubre de 202224 de abril de 202431 de enero de 2023
    Comentar
  • Increase in the number of women taking on permanent jobs at Rogun PMG at technical and managerial levelsValor5.003.0010.00
    Fecha17 de octubre de 202324 de abril de 202431 de diciembre de 2024
    Comentar
  • Update of E&S instruments of Rogun HPP Project is completedValorNoNoYes
    Fecha31 de octubre de 202224 de abril de 202431 de diciembre de 2024
    Comentar
  • Percentage of citizens who believe that the Project has established effective engagement processesValorTo be established during 2022 surveyto be yet determinedAt least 65 percent
    Fecha31 de marzo de 202324 de abril de 202431 de diciembre de 2026
    Comentar
  • Electricity market analysis is completed and the PPAs for sale of Rogun electricity are draftedValorNoNoYes
    Fecha31 de octubre de 202223 de abril de 202430 de abril de 2023
    Comentar
  • Preparation of Rogun HPP Project community benefit sharing program is completedValorNoNoYes
    Fecha31 de octubre de 202224 de abril de 202431 de enero de 2024
    Comentar