Sri Lanka Public Financial Management Strengthening Project

Resumen*

The project is aligned with and supports selected governance reforms as prioritized by the GoSL. The project will support: (i) the improvement of procurement outcomes through enhancement of the existing e-procurement system, including open contracting standards and the roll-out of new modules covering national and international bidding and functionalities in key service delivery ministries to enhance transparency and accountability; and (ii) enhance...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

To enhance the institutional capacity and transparency in procurement and external audit.

Llave Detalles

Proyecto Detalles

  • P178432

  • Active

  • Mohan Gopalakrishnan , Heenaben Doshi

  • Democratic Socialist Republic of Sri Lanka

  • Sri Lanka

  • 8 de febrero de 2023

  • (a partir de la presentación ante el Directorio)

    27 de junio de 2023

  • 6 de julio de 2023

  • US$ 7.10 millones

  • NATIONAL AUDIT OFFCIE OF SRI LANKA,Ministry of Finance, Economic Stabilization and National Policies - Public Finance Department,National Audit Office of Sri Lanka

  • Asia meridional

  • 2023

  • US$ 4.20 millones

  • N/A

  • 9 de octubre de 2023

  • 30 de noviembre de 2026

  • Yes

  • BANK APPROVED

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
Miscellaneous 1 4.20

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF No Disponible
Compromiso de la AIF No Disponible
Compromiso del BIRF + AIF No Disponible
Instrumento de Financiamiento
Monto a título de donación 4.20
Costo total del proyecto** 7.10

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Procurement Moderately Satisfactory 2024-11-08
Progress towards achievement of PDO Moderately Satisfactory 2024-11-08
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-11-08
Project Management Moderately Satisfactory 2024-11-08
Financial Management Satisfactory 2024-11-08
Monitoring and Evaluation Satisfactory 2024-11-08

CALIFICACIONES DE LA TERMINACIÓN

No hay datos disponibles.

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

No hay datos disponibles.

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Specialized audits carried out by NAOSL that are made publicly availableValorA limited number of specialized audits carried outYet to be initiatedAudit reports of specialized audits available in p
    Fecha31 de diciembre de 20226 de octubre de 202330 de noviembre de 2026
    Comentar
  • Information available in the public domain on procurement opportunitiesValorInformation on shopping procurement using e-procurInformation on shopping procurement using e-procurEnhanced access to information on procurement oppo
    Fecha31 de diciembre de 20226 de octubre de 202330 de noviembre de 2026
    Comentar
  • Reduction in procurement cycle time in at least two procurement entities with significant procurement volumesValorLack of information on procurement cycle time in pBaseline survey to be initiated in two MDAs10 percent reduction in time taken for procurement
    Fecha31 de diciembre de 20226 de octubre de 202330 de noviembre de 2026
    Comentar
  • NAOSL’s capacity developed to undertake participatory auditsValorLimited engagement of citizens in the audit procesEngagement with potential peer SAIs initiatedNAOSL’s institutional capacity for participatory a
    Fecha31 de diciembre de 20226 de octubre de 202330 de noviembre de 2026
    Comentar

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • E-procurement system established and operationalValorThere is an e-procurement system that provides theA draft implementation plan has been prepared. TheAn E-procurement system covering various methods o
    Fecha30 de noviembre de 20226 de octubre de 202330 de noviembre de 2026
    Comentar
  • Improvement in performance rating of NAOSL in selected priority indicators as per SAI-PMF AssessmentValorNAOSL performing between the founding and establisNAOSL is in the process of engaging a consultant tIncrease in NAOSL’s SAI-PMF Assessment rating in p
    Fecha29 de noviembre de 20196 de octubre de 202330 de noviembre de 2026
    Comentar
  • Scale up of existing modules and roll out of new modules of the e-GP systemValorShopping module rolled out in 40 pilot procuring eOf the 301 procuring entities (PE) registered at tE-Procurement system rolled out to all procuring e
    Fecha30 de diciembre de 20226 de octubre de 202330 de noviembre de 2026
    Comentar
  • Capacity Building of NAOSL staff in specialized Audits (No. of staff trained)ValorLimited and absence of structured training in specUpdate of manuals yet to be initiatedThe capacity of NAOSL staff enhanced to carry out
    Fecha30 de diciembre de 20226 de octubre de 202330 de noviembre de 2026
    Comentar
  • Of which No. of staff trained are femaleValorNilNil40 female staff have received specialized training
    Fecha30 de diciembre de 202228 de septiembre de 202330 de noviembre de 2026
    Comentar
  • Information on contract award in public domainValorContract award information not available in publicMoF has mandated the e-publication of contract awa60 percent of shopping procurement and 50 percent
    Fecha31 de diciembre de 20226 de octubre de 202330 de noviembre de 2026
    Comentar
  • Enhanced access and use of audit management software (AMS) and Computer Assisted Audit Techniques (CAAT)ValorOutdated AMS and no CAAT tools in useConsultant to study the existing AMS and appropriaEnhanced efficiency in audits by NAOSL through use
    Fecha31 de diciembre de 20226 de octubre de 202330 de noviembre de 2026
    Comentar