Skip to Main Navigation

Central Africa Regional Waterways Project

Resumen*

With a population of nearly 5.4 million, the CAR is a sparsely populated, landlocked country in the heart of Africa. Despite its vast 623,000 km² area, rich in arable land, large mineral deposits, and dense tropical forests, CAR remains one of the poorest nations in Africa. Agriculture dominates the economy, employing 80% of the active population and contributing to half of the country's GDP. However, with a GDP per capita of US$ 775, CAR faces immense...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

The Project Development Objective is to enhance transport and trade efficiency, infrastructure climate-resilience, and socio-economic inclusion, along the selected waterway and road corridor sections between the Central African Republic (CAR) and Republic of Congo (ROC).

Llave Detalles

Proyecto Detalles

  • P175235

  • Active

  • Oceane Keou , Thierry Davy, Francis Ovanda Mbele

  • Republic of Congo,Central African Republic

  • África central

  • 3 de marzo de 2022

  • (a partir de la presentación ante el Directorio)

    29 de junio de 2023

  • 18 de marzo de 2024

  • US$ 300.00 millones

  • Ministry of Equipment and Public Works (CAR),Ministry of Digital Economy, Posts, and Telecommunications (CAR),Ministry of the River Economy and Waterways (ROC),Ministry of Planning, Statistics and Regional Integration (ROC),Ministry of Transport and Civil Aviation (CAR)

  • Western and Central Africa

  • 2023

  • US$ 330.00 millones

  • N/A

  • 5 de abril de 2024

  • 31 de octubre de 2029

  • Yes

  • BANK APPROVED

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
IDA Credit 90.00
IDA Grant 240.00

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF No Disponible
Compromiso de la AIF 330.00
Compromiso del BIRF + AIF 330.00
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 300.00

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-12-31
Monitoring and Evaluation Satisfactory 2024-12-31
Procurement Satisfactory 2024-12-31
Financial Management Moderately Satisfactory 2024-12-31
Project Management Moderately Satisfactory 2024-12-31
Overall Implementation Progress (IP) Satisfactory 2024-12-31

CALIFICACIONES DE LA TERMINACIÓN

No hay datos disponibles.

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

No hay datos disponibles.

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Reduced travel time along the Brazzaville-Bangui waterway and the Bossembélé-Bossangoa road sectionsValor0.000.0030.00
    Fecha15 de marzo de 202329 de marzo de 202431 de octubre de 2029
    Comentar
  • People provided with all-weather access along the Brazzaville-Bangui waterway and Bossembélé-Bossangoa road sectionsValor0.000.002922000.00
    Fecha15 de marzo de 202329 de marzo de 202431 de octubre de 2029
    Comentar
  • Share of targeted local traders in CAR and ROC demonstrating improved trade and business competencyValor0.000.0075.00
    Fecha15 de marzo de 202329 de marzo de 202431 de octubre de 2029
    Comentar
  • Reduced travel time along the Bossembélé-Bossangoa road sectionValor260.000.000.00
    Fecha
    Comentar
  • People provided with all-weather access along the Bossembélé-Bossangoa road sectionValor0.000.001341000.00
    Fecha15 de marzo de 202329 de marzo de 202431 de octubre de 2029
    Comentar
  • of which are female tradersValor0.000.000.00
    Fecha
    Comentar
  • Reduced travel time along the Brazzaville-Bangui waterway sectionValor14.000.000.00
    Fecha
    Comentar
  • People provided with all-weather access along the Brazzaville-Bangui waterway sectionValor0.000.001581000.00
    Fecha15 de marzo de 202329 de marzo de 202431 de octubre de 2029
    Comentar
  • Share of targeted local traders in CAR demonstrating improved trade and business competencyValor0.000.0075.00
    Fecha15 de marzo de 202329 de marzo de 202431 de octubre de 2029
    Comentar
  • Increased throughput at selected ports along the Brazzaville-Bangui waterway sectionValor0.000.0010.00
    Fecha15 de marzo de 202329 de marzo de 202431 de octubre de 2029
    Comentar
  • Share of targeted local traders in ROC demonstrating improved trade and business competencyValor0.000.0075.00
    Fecha15 de marzo de 202329 de marzo de 202431 de octubre de 2029
    Comentar

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Villages provided with new or rehabilitated socio-economic infrastructureValor0.000.0010.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Digital trade data collection system established in CAR and ROCValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Grievances resolved related to the delivery of project activities within the timeframe stipulated in the PIMValor0.000.00100.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • GIE-SCEVN annual campaigns for maintenance and replacement of river markings and buoys completedValor0.000.005.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Training person-days completed (certification/training programs on navigation)Valor0.000.0012000.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Ports and quays rehabilitated or upgraded with green, climate-resilient and universal access standardsValor0.000.0018.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Community feedback on community-level infrastructure worksValor0.000.0080.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Bossembele-Bossangoa road section upgraded to 2-lane climate-resilient paved road standardValor0.000.00150.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Share of project-funded storage facilities leased to or used by women in local marketsValor0.000.0060.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • of which are female beneficiariesValor0.000.000.00
    Fecha
    Comentar
  • All-weather connection for people in Bossangoa along project feeder roadsValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Congo Basin Information System (SIBCO), including early warning system, upgradedValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Green and Resilient Ports and Waterways Development Strategies in ROC and CAR endorsedValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Green and Resilient Ports and Waterways Development Strategy in CAR endorsedValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Green and Resilient Ports and Waterways Development Strategy in ROC endorsedValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Financially sustainable asset management strategies for the whole corridor endorsedValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Financially sustainable asset management strategy for road corridors in CAR updated and endorsedValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Financially sustainable asset management strategy for the ports in CAR developed and endorsedValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Financially sustainable asset management strategy for the ports in ROC developed and endorsedValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Financially sustainable strategy for waterways maintenance along the Brazzaville-Bangui waterway corridor developed and endorsedValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Zinga feasibility study completedValorNoNoYes
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Road and navigation safety awareness campaigns implementedValor0.000.008.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Road safety awareness campaigns implementedValor0.000.004.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar
  • Navigation safety awareness campaigns implementedValor0.000.004.00
    Fecha15 de marzo de 202320 de septiembre de 202331 de octubre de 2029
    Comentar