Lima Metropolitano BRT North Extension

Resumen*

The proposed Project is the continuation of Lima Transport Project (P035740) financed by the Bank and implemented from 2003 to 2010. The area of influence of the Project is comprised by four districts in the North Lima: Independencia, Comas, Los Olivos and Carabayllo. This project will benefit: (a) 1,460,000 residents of four districts in North Lima; and (b) result in 150,653 trips per day in North Lima. Low-income users living in the area of influence...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

The Project Development Objective (PDO) is to improve urban mobility and accessibility to jobs in the area of influence of the Metropolitano BRT North Extension.

Llave Detalles

Proyecto Detalles

  • P170595

  • Closed

  • Felipe Targa Rodriguez , Yang Chen

  • Republic of Peru

  • Perú

  • 3 de mayo de 2019

  • (a partir de la presentación ante el Directorio)

    30 de enero de 2020

  • 19 de junio de 2020

  • US$ 123.00 millones

  • Metropolitan Municipality of Lima with the assistance of EMAPE

  • América Latina y el Caribe

  • 2020

  • US$ 93.00 millones

  • N/A

  • Substantial

  • 30 de abril de 2024

  • No

  • BANK APPROVED

  • 22 de marzo de 2024

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
Borrower/Recipient 30.00
International Bank for Reconstruction and Development 93.00

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF 93.00
Compromiso de la AIF No Disponible
Compromiso del BIRF + AIF 93.00
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 123.00

Resumen del financiamiento del Banco Mundial (millones de US$) al 30 de abril de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 30 de abril de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Project Management Moderately Satisfactory 2023-11-08
Monitoring and Evaluation Satisfactory 2023-11-08
Overall Implementation Progress (IP) Moderately Satisfactory 2023-11-08
Counterpart Funding Satisfactory 2023-11-08
Financial Management Unsatisfactory 2023-11-08
Progress towards achievement of PDO Moderately Unsatisfactory 2023-11-08
Procurement Moderately Satisfactory 2023-11-08

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 10-28-2024
ResultadosModerately Unsatisfactory
Riesgo para los resultados de desarrollo
Desempeño del BancoModerately Unsatisfactory
Desempeño del prestatario
Desempeño del Gobierno
Organismo Ejecutor

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 03-07-2025INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO:
Calificación De Los ResultadosModerately Unsatisfactory N/a
Riesgo Para Los Resultados De DesarrolloN/a
Desempeño Del BancoModerately UnsatisfactoryN/a
Desempeño Del PrestatarioN/a
Desempeño Del GobiernoN/a
Organismo EjecutorN/a
Calidad Del IfeSubstantialN/a
Calidad De SyeModestN/a

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • In-vehicle travel time for public transport users between Terminal Chimpu Ocllo and Terminal NaranjalValor31.0031.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Average number of jobs reachable by public transportation within a 60-minute, one-way commute in the area of influence of the Metropolitano BRT North Extension (number)Valor156595.00156595.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Passengers’ trips per day in the Metropolitano BRT North Extension, differentiated by socioeconomic levels and genderValor0.000.0030000.00
    Fecha31 de mayo de 202130 de septiembre de 202331 de diciembre de 2021
    Comentar
  • Low-income passengers as % of total validations entering the northern terminals of the Metropolitano BRT systemValor31.0031.000.00
    Fecha
    Comentar
  • Women passengers per day as % of total validations on the Metropolitano BRT North Extension (feeder and trunk buses)Valor0.000.000.00
    Fecha
    Comentar
  • Women passengers shifting from informal transport modes to the Metropolitano BRT North Extension, as % of total surveyed womenValor0.000.000.00
    Fecha
    Comentar
  • Users satisfied with the service in the northern BRT extension (coverage, reliability, safety, personal security), differentiated by socioeconomic level and genderValor56.0035.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Change in % of women passengers satisfied with service in terms of safety, securityValor0.000.000.00
    Fecha
    Comentar

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Improved the capacity of Protransporte's bus scheduling task teamValorNoNo
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Physical progress in building segregated BRT lanes on the Metropolitano BRT North ExtensionValor0.0099.900.00
    Fecha12 de junio de 201930 de septiembre de 2023
    Comentar
  • Diagnosis and improvement of service plans, route scheduling, and bus dispatch services completedValorNoNo
    Fecha
    Comentar
  • Roads constructedValor0.0010.200.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Roads constructed - non-ruralValor0.000.000.00
    Fecha
    Comentar
  • State-of-the-art software and methodology for scheduling feeder and trunk services implementedValorNoNo
    Fecha
    Comentar
  • Enhanced M&E framework for monitoring operational performance indicators on the Metropolitano BRTValorNoNo
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Physical progress in constructing passenger stations on the Metropolitano BRT North ExtensionValor0.0099.900.00
    Fecha12 de junio de 201930 de septiembre de 2023
    Comentar
  • Operational efficiencies implementedValor0.000.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Passenger stations that provide access for people with disabilitiesValor0.000.000.00
    Fecha
    Comentar
  • Updated and upgraded feeder-route service planValor0.000.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Physical progress in constructing pedestrian bridges on the Metropolitano BRT North ExtensionValor0.00100.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Updated trunk service planValor0.000.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Construction of U-turns on the Metropolitano BRT North ExtensionValor0.003.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Implementation plan for an expanded, integrated and improved the fare collection system on the entire Metropolitano BRT systemValorNoNo
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Physical progress of expanding a bus depot on the Metropolitano BRT North ExtensionValor0.0098.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Integration and expansion of the existing Metropolitano BRT fare collection system with the North Extension (including feeder routes) completedValorNoNo
    Fecha
    Comentar
  • Carriageway-km covered by installing infrastructure and/or equipment designed to reduce speedsValor0.0010.200.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Share of personalized smart cards as % of total active smart cards for the Metropolitano BRT systemValor0.000.000.00
    Fecha
    Comentar
  • Integrated the Metropolitano BRT North Extension to the BRT system based on the preoperational planValorNoNo
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Citizens reporting satisfaction with key aspects of consultation process, disintegrated by genderValor0.000.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Harmonized Response Protocol to address cases of sexual harassment in the Metropolitano BRT being used by ProtransporteValorNoYes
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Women employed in the Metropolitano BRTValor13.0013.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Construction workers in the Metropolitano BRT North Extension that have signed the code of conduct and attended the code of conducttrainingValor0.00100.000.00
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar
  • Implementation the environmental management measures for the project’s green areas following the specifications of the approved final Vegetation Management PlanValorNoYes
    Fecha31 de mayo de 202130 de septiembre de 2023
    Comentar