Skip to Main Navigation

Tunisia - Northern Tunis Wastewater Project Additional Financing

Objetivo de desarrollo

The project development objective is to provide an environmentally safe disposal system for the treated wastewater in the North of Tunis, and increase availability for its reuse in the Project Area.

Llave Detalles

Proyecto Detalles

  • P154713

  • Closed

  • Jean-Martin Brault

  • N/A

  • Túnez

  • 21 de abril de 2015

  • (a partir de la presentación ante el Directorio)

    31 de agosto de 2016

  • N/A

  • US$ 18.00 millones

  • A

  • 14 de noviembre de 2022

  • 30 de junio de 2021

  • No

  • BANK APPROVED

  • P117082

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
International Bank for Reconstruction and Development 18.00
Borrower/Recipient 5.00

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF 18.00
Compromiso de la AIF No Disponible
Compromiso del BIRF + AIF 18.00
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 23.00

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

No hay datos disponibles.

CALIFICACIONES DE LA TERMINACIÓN

No hay datos disponibles.

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

No hay datos disponibles.

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Percentage of TWW (not reused in the irrigation) from Northern Tunis WWTP discharged at the submarine outfallValor0.000.00100.00
    Fecha3 de mayo de 201031 de diciembre de 201330 de junio de 2017
    Comentar
  • Percentage of seawater samples at Raoued Beach complying with imperative norms in total coliforms and fecal coliforms (respectively10,000 TC/100ml and 2,000 FC/100ml).Valor80.000.0090.00
    Fecha31 de diciembre de 201531 de diciembre de 201631 de diciembre de 2019
    ComentarBaseline value is estimated based on data from ESMP baseline report, to be re-confirmed once second year of data is available.TBCScope and target correspond to Class B bathing areas according to MedPol program (EU standards), i.e. of average quality.
  • Average annual volume of TWW made available to farmers, developers or municipalities in the vicinity of the ProjectValor0.000.003000000.00
    Fecha31 de diciembre de 201031 de mayo de 201631 de diciembre de 2019
    Comentar
  • Average annual concentration of suspended solids in TWW made available at the El Hissiène basinValor120.000.0030.00
    Fecha31 de diciembre de 201531 de diciembre de 201631 de diciembre de 2019
    ComentarBaseline value is estimated based on historic data monitored by regional agriculture district, on quality of TWW which farmerscurrently use.TBC - Current value cannot be assessed until the basin is online, once transfer system is completed.Target is a lower threshold value, corresponds to Tunisian norm NT106.03.
  • Direct project beneficiariesValor0.000.0050000.00
    Fecha31 de diciembre de 201031 de mayo de 201631 de diciembre de 2019
    ComentarTarget set based on ONAS estimate in March 2015
  • Female beneficiariesValor0.000.0050.00
    Fecha31 de diciembre de 201031 de mayo de 201631 de diciembre de 2019
    Comentar
  • Average annual count of fecal coliforms in seawater samples in the surrounding of the outfallValor200.000.002000.00
    Fecha31 de diciembre de 201531 de diciembre de 201631 de diciembre de 2019
    ComentarBaseline value is estimated based on data from ESMP baseline report, to be re-confirmed once second year of data is available.TBCTarget is set so that seawater quality remains within Tunisian norm NT106.02 despite outfall discharge.

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Average annual concentration of suspended solids in TWW at the entry point of the transfer systemValor120.000.0030.00
    Fecha31 de diciembre de 201031 de diciembre de 201631 de diciembre de 2019
    ComentarBaseline value is estimated based on historic data monitored by regional agriculture district, on quality of TWW it pumps forfarmers.Baseline and current value will be confirmed with stakeholders based on more recent measurements, which have not been madeavailable yet.Target is a lower threshold value, corresponds to Tunisian norm NT106.02.
  • Average annual count of fecal coliforms in seawater samples at Raoued beachValor450.000.00100.00
    Fecha31 de diciembre de 201531 de diciembre de 201631 de diciembre de 2019
    ComentarBaseline value is estimated based on data from ESMP baseline report, to be re-confirmed once second year of data is available.Target is a lower threshold value, corresponds to Tunisian norm NT09.11.
  • Percentage of TWW (not reused) from Northern Tunis WWTP discharged at the submarine outfallValor0.000.0095.00
    Fecha31 de diciembre de 201031 de mayo de 201631 de diciembre de 2019
    Comentar
  • Volume (in m3 per year) of TWW available for potential reuse in agricultureValor0.000.0030000000.00
    Fecha3 de mayo de 201031 de diciembre de 201330 de junio de 2017
    Comentar
  • Volume (in m3 per year) of TWW discharged into the submarine outfall at the regulation basinValor0.000.0070000000.00
    Fecha3 de mayo de 201031 de marzo de 201530 de junio de 2018
    Comentar
  • Length of pipe installedValor0.002500.0012000.00
    Fecha31 de diciembre de 201031 de mayo de 201631 de diciembre de 2019
    Comentar
  • Percentage of samples of TWW made available for irrigation complying with the Tunisian norm NT106.03 for BOD5Valor0.000.0075.00
    Fecha3 de mayo de 201031 de marzo de 201530 de junio de 2018
    Comentar
  • Volume (in m3 per annum) of TWW made available to farmers, developers or municipalities in the vicinity of the ProjectValor0.000.003000000.00
    Fecha3 de mayo de 201031 de marzo de 201530 de junio de 2018
    Comentar
  • Beneficiaries that feel project investments reflected their needs (percentage)Valor0.000.0080.00
    Fecha3 de mayo de 201031 de marzo de 201530 de junio de 2018
    Comentar
  • Grievances registered related to delivery of project benefits addressed (%)Valor0.000.0075.00
    Fecha31 de diciembre de 201031 de mayo de 201631 de diciembre de 2019
    Comentar
  • Beneficiaries that feel project inv. reflected their needs - female (number)Valor0.000.0020000.00
    Fecha3 de mayo de 201031 de marzo de 201530 de junio de 2018
    Comentar
  • Total beneficiaries - female (number)Valor0.000.0025000.00
    Fecha3 de mayo de 201031 de marzo de 201530 de junio de 2018
    Comentar
  • Total beneficiaries - male (number)Valor0.000.0025000.00
    Fecha3 de mayo de 201031 de marzo de 201530 de junio de 2018
    Comentar
  • Beneficiaries that feel project inv. reflected their needs - male (number)Valor0.000.0020000.00
    Fecha3 de mayo de 201031 de marzo de 201530 de junio de 2018
    Comentar
  • Grievances related to delivery of project benefits that are addressed-(number)Valor0.000.00100.00
    Fecha31 de diciembre de 201031 de mayo de 201631 de diciembre de 2019
    Comentar
  • Average annual concentration of suspended solids in TWW made available at the Sidi Amor reuse pilotValor120.000.0030.00
    Fecha31 de diciembre de 201031 de diciembre de 201631 de diciembre de 2019
    ComentarBaseline value is estimated based on historic data monitored by regional agriculture district, on quality of TWW which farmerscurrently use.Current value cannot be assessed until the pilot is running for a few months (by December 2016).Target is a lower threshold value, corresponds to Tunisian norm NT106.03. Value based on measurements at the pilot laboratory.