EC Ibarra Transport Infrastructure Improvement Project

Resumen*

The development objective of the Ibarra Transport Infrastructure Improvement Project for Ecuador is to improve mobility in Ibarra and the use of recreational spaces in the Yahuarcocha Lagoon area. The project comprises of four components. The first component, improve mobility in the city will improve traffic flows by providing better access to the city center and mobility for through traffic and relieve congestion within the city center (including...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

The Project Development Objective (PDO) is to improve mobility of Ibarra and the use of recreational spaces in the Yahuarcocha lagoon area, and to respond effectively in case of an Eligible Crisis or Emergency

Llave Detalles

Proyecto Detalles

  • P147280

  • Closed

  • Alejandro Hoyos Guerrero

  • Municipality of Ibarra

  • Ecuador

  • 16 de diciembre de 2013

  • (a partir de la presentación ante el Directorio)

    27 de enero de 2016

  • 28 de marzo de 2017

  • US$ 91.03 millones

  • Municipality of Ibarra UGP

  • América Latina y el Caribe

  • 2016

  • US$ 52.50 millones

  • B

  • N/A

  • 30 de junio de 2024

  • TBD

  • BANK APPROVED

  • 14 de febrero de 2024

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
Borrower/Recipient 20.09
International Bank for Reconstruction and Development 52.50

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF 52.50
Compromiso de la AIF No Disponible
Compromiso del BIRF + AIF 52.50
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 91.03

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-06-27
Financial Management Moderately Satisfactory 2024-06-27
Overall Safeguards Rating Satisfactory 2024-06-27
Procurement Moderately Satisfactory 2024-06-27
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-06-27
Project Management Unsatisfactory 2024-06-27
Monitoring and Evaluation Unsatisfactory 2024-06-27

CALIFICACIONES DE LA TERMINACIÓN

No hay datos disponibles.

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

No hay datos disponibles.

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Average travel time by private transport to area hospitals from select low-income areas influenced by the Ring Road.Valor34.1124.0324.11
    Fecha1 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar
  • Percentage of visitors who use a bicycle and walk in YahuarcochaValor18.0045.0024.00
    Fecha1 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar
  • Share of business owners in Yahuarcocha Lagoon business area whose monthly income level is at or exceeds the minimum wageValor45.0068.1264.00
    Fecha3 de abril de 201715 de octubre de 202330 de junio de 2024
    Comentar
  • Number of people in Azaya-Alpachaca neighborhood who can access the city center by public transport in 25 minutes or less.Valor1683.008417.006000.00
    Fecha1 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Number of yearly visitors to YahuarcochaValor663600.00370950.00729960.00
    Fecha1 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar
  • Road asset management plan preparedValorNoYesYes
    Fecha1 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar
  • Proposed organization chart adoptedValorNoYesYes
    Fecha1 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar
  • Progress of construction and restoration of tourist spaces works on Yahuarcocha BoulevardValor0.00100.00100.00
    Fecha1 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar
  • Study for the improvement of sustainable mobility in Ibarra preparedValorNoNoYes
    Fecha1 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar
  • Share of Project beneficiaries expressing satisfaction with the Ring Boulevard infrastructure and mobility optionsValor0.0087.0075.00
    Fecha1 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar
  • Share of female beneficiaries expressing satisfactionValor0.0086.000.00
    Fecha
    Comentar
  • People with enhanced access to transportation servicesValor0.00100000.00200000.00
    Fecha5 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar
  • People with enhanced access to transportation services - Urban TransportValor0.00100000.00200000.00
    Fecha5 de enero de 201630 de septiembre de 202230 de junio de 2024
    Comentar
  • Roads constructedValor0.009.509.50
    Fecha5 de enero de 201615 de octubre de 202330 de junio de 2024
    Comentar
  • Roads constructed - non-ruralValor0.009.500.00
    Fecha
    Comentar