The development objective of the Development Policy Loan (DPL) program is to support the Government of Morocco (GoM) in implementing its program of reforms aimed at improving the financial, environmental and social performance of the municipal solid waste sector in Morocco. The first DPL supported the key foundations of the Government's reform program, which established the enabling environment for an integrated and affordable municipal solid waste...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

The objective is to support the government in implementing its program for the reform of the municipal solid waste sector in Morocco through: (i) enhancing the governance of the sector; (ii) improving the sustainability of municipal solid waste services; and (iii) mainstreaming environmental and social dimensions.

Llave Detalles

Proyecto Detalles

  • P119781

  • Closed

  • Jaafar Sadok Friaa

  • N/A

  • Marruecos

  • 20 de mayo de 2010

  • (a partir de la presentación ante el Directorio)

    20 de diciembre de 2010

  • 18 de mayo de 2011

  • US$ 138.60 millones

  • N/A

  • 15 de enero de 2013

  • 31 de diciembre de 2011

  • BANK APPROVED

  • P104937

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
International Bank for Reconstruction and Development 138.60

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF 138.60
Compromiso de la AIF No Disponible
Compromiso del BIRF + AIF 138.60
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 138.60

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Progress towards achievement of PDO Satisfactory 2011-02-21
Monitoring and Evaluation Satisfactory 2011-02-21
Overall Implementation Progress (IP) Satisfactory 2011-02-21
Program Management Satisfactory 2011-02-21

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 06-26-2012
ResultadosSubstantial
Riesgo para los resultados de desarrolloModest
Desempeño del BancoSubstantial
Desempeño del prestatarioSubstantial
Desempeño del GobiernoSubstantial
Organismo EjecutorSubstantial

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 12-14-2021INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO: 12-11-2013
Calificación De Los ResultadosModerately Satisfactory Moderately Satisfactory
Riesgo Para Los Resultados De DesarrolloSignificantModerate
Desempeño Del BancoSatisfactorySatisfactory
Desempeño Del PrestatarioSatisfactorySatisfactory
Desempeño Del GobiernoSatisfactory
Organismo EjecutorSatisfactory
Calidad Del IfeSatisfactory
Calidad De SyeModest

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Annual costed -workplans and progress reports are systematically reviewed and adopted by the CN-PNDM.Valor03 progress reports and 2 annual programs6 progress reports and 3 annual programs
    Fecha30 de diciembre de 200830 de noviembre de 201030 de mayo de 2012
    Comentar
  • Percentage of total government financial support under the PNDM allocated based on the adopted eligibility criteria.Valor0.0050.00100.00
    Fecha30 de diciembre de 200830 de noviembre de 201030 de mayo de 2012
    Comentar
  • Solid waste infrastructure supported through the PNDM is consistent with national regulations, based on reviews of projects (to be verified by project sampling in Q3 FY12).Valor0.000.00100.00
    Fecha30 de diciembre de 200830 de noviembre de 201030 de mayo de 2012
    Comentar
  • Increased competition in tenders for MSWM, as measured by the increase in number of received bids between 2008 and 2011, reported at bid opening records.Valor4 to 5 bids per tenderSignificant improvement in term of bidder particip
    Fecha30 de diciembre de 200830 de noviembre de 201030 de mayo de 2012
    Comentar
  • Number of thematic conventions signed between local governments and the State targeting the upgrade of MSWMValor0.003.0010.00
    Fecha30 de diciembre de 200830 de noviembre de 201030 de mayo de 2012
    Comentar
  • Change in the perception by the urban population of MSWM as a priority area of intervention, as measured by sample survey.ValorN/AN/A
    Fecha
    Comentar
  • Improved coverage of the costs of SWM services in municipalities supported by the PNDM.Valor172840000.000.00370000000.00
    Fecha30 de diciembre de 2011
    Comentar
  • Number of local governments benefitting from capacity-building activitiesValor0.000.000.00
    Fecha30 de diciembre de 2008
    Comentar
  • Number of EIAs related to solid waste investments reviewed and approved by regional or national EIA committeesValor0.0017.000.00
    Fecha
    Comentar
  • Percentage of collected waste disposed in sanitary landfills by 2012Valor0.0028.0030.00
    Fecha30 de noviembre de 201030 de mayo de 2012
    Comentar
  • Number of open dumpsites closed/ rehabilitated by 2012Valor4.000.000.00
    Fecha30 de noviembre de 2010
    Comentar
  • Number of wastepickers benefiting from social inclusion initiativesValor0.000.00100.00
    Fecha30 de mayo de 2012
    Comentar