Income Support and Employability Project

Resumen*

The objectives of the Income Support and Employability Project for El Salvador are to: (i) provide temporary income support to the urban vulnerable poor; (ii) improve the coverage of labor intermediation and training services, to the urban vulnerable poor; and (iii) improve the institutional capacity of the Borrower to develop an integrated social protection system. There are three components to the project: (1) the design and implementation of a...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

The proposed Project aims to support the Government of El Salvador in its short-term response to the crisis, while at the same time contributing to the establishment of an integrated social protection system. Within this context, the Project development objectives are to: (i) provide temporary income support to the urban vulnerable poor; (ii) improve the coverage of labor intermediation and training services to the urban vulnerable poor; and (iii) improve the institutional capacity of the Borrower to develop an integrated social protection system.

Llave Detalles

Proyecto Detalles

  • P117440

  • Closed

  • Nancy Banegas Raudales , Edmundo Murrugarra

  • Ministerio de Hacienda

  • El Salvador

  • 1 de octubre de 2009

  • (a partir de la presentación ante el Directorio)

    24 de noviembre de 2009

  • 18 de enero de 2011

  • US$ 54.00 millones

  • Secretaria Tecnica y de Planificacion de la Presidencia,Fondo de Inversion Social para el Desarrollo Local,Ministerio de Trabajo y Prevision Social

  • América Latina y el Caribe

  • 2010

  • US$ 50.00 millones

  • B

  • 12 de septiembre de 2023

  • 31 de agosto de 2016

  • BANK APPROVED

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
International Bank for Reconstruction and Development 50.00
Borrower/Recipient 4.00

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF 50.00
Compromiso de la AIF No Disponible
Compromiso del BIRF + AIF 50.00
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 54.00

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Procurement Moderately Satisfactory 2016-08-25
Financial Management Moderately Satisfactory 2016-08-25
Progress towards achievement of PDO Satisfactory 2016-08-25
Project Management Satisfactory 2016-08-25
Counterpart Funding Satisfactory 2016-08-25
Monitoring and Evaluation Satisfactory 2016-08-25
Overall Implementation Progress (IP) Satisfactory 2016-08-25

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 02-24-2017
Resultados
Riesgo para los resultados de desarrolloSubstantial
Desempeño del Banco
Desempeño del prestatario
Desempeño del Gobierno
Organismo Ejecutor

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 06-16-2017INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO: 04-23-2019
Calificación De Los ResultadosSatisfactory Satisfactory
Riesgo Para Los Resultados De DesarrolloSubstantialSubstantial
Desempeño Del BancoSatisfactorySatisfactory
Desempeño Del PrestatarioSatisfactoryModerately Satisfactory
Desempeño Del GobiernoSatisfactoryNot Rated
Organismo EjecutorSatisfactorySatisfactory
Calidad Del IfeHighNot Rated
Calidad De SyeSubstantialSubstantial

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Number of individuals that receive PATI income supportValor0.0047456.0043000.00
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Normative framework for the SPSU has been approved by the SPSU Inter-Sectoral CommitteeValorNoYesYes
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Increase in the number of 18 to 25 years old enrolled in the RNEValor3700.0026642.0011000.00
    Fecha1 de noviembre de 200931 de marzo de 201631 de agosto de 2016
    Comentar

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Percentage of individuals aged 16 years or older in targeted settlements that are covered by PATIValor0.0022.0015.00
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Percent of female PATI participantsValor0.0070.8160.00
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Percentage of PATI participants that completed the training and activity requirementsValor0.0086.4090.00
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Percent youth among PATI participantsValor0.0037.0040.00
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Increase in the number of individuals enrolled in the RNEValor23572.0075531.0050000.00
    Fecha1 de noviembre de 200931 de marzo de 201631 de agosto de 2016
    Comentar
  • Number of established employment officesValor28.0049.0066.00
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Increase in the percentage of the enrolled population in the RNE that are womenValor47.0053.0053.00
    Fecha1 de noviembre de 200931 de marzo de 201631 de agosto de 2016
    Comentar
  • Increase in the percentage of the enrolled population without complete secondary educationValor41.0060.0060.00
    Fecha1 de noviembre de 200931 de marzo de 201631 de agosto de 2016
    Comentar
  • Number of new employers enrolling in the RNEValor384.005059.00800.00
    Fecha1 de noviembre de 200931 de marzo de 201631 de agosto de 2016
    Comentar
  • Number of employment fares organizedValor32.0066.0050.00
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Number of job seekers participating in employment fairsValor21860.0053568.0040000.00
    Fecha1 de noviembre de 200931 de marzo de 201631 de agosto de 2016
    Comentar
  • Labor Market Monitoring Unit (Observatorio del Mercado Laboral, OML) up and runningValorNoYesYes
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Percentage of Comunidades Solidarias participants registered in the Unique Registry of Beneficiaries (RUP)Valor0.0061.6075.00
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Percentage of Comunidades Solidarias programs which have been incorporated into the Social Information System of the SPSUValor0.0025.0075.00
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar
  • Normative framework for the Unique Registry of Beneficiaries (RUP) approved by the SPSU Inter-Sectoral CommitteeValorNoYesYes
    Fecha1 de noviembre de 200929 de julio de 201631 de agosto de 2016
    Comentar