Pakistan: Lahore Composting project

Objetivo de desarrollo

The overarching development objectives of the proposed Carbon Finance project are to: # Avoid generation of methane emission from biodegradable wastes; and # Improve cultivated land by using compost as a natural soil conditioner The Carbon Finance project will provide additional support for achieving the following objectives and benefits, namely to reduce carbon emission in a financially sustainable way, to promote and provide organic conditioner for agriculture; to increase recycling of valuable materials; to reduce health hazard by overall reduction of waste disposed off in landfills; and reduce the demand for landfill capacity.

Llave Detalles

Proyecto Detalles

  • P106652

  • Closed

  • Claudia Croce

  • N/A

  • Pakistán

  • 18 de junio de 2008

  • (a partir de la presentación ante el Directorio)

    27 de agosto de 2008

  • 27 de agosto de 2008

  • US$ 5.52 millones

  • N/A

  • Asia meridional

  • 2009

  • US$ 5.52 millones

  • N/A

  • No aplicable

  • 26 de julio de 2016

  • BANK APPROVED

  • 19 de diciembre de 2024

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
Carbon Fund 5.52

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF No Disponible
Compromiso de la AIF No Disponible
Compromiso del BIRF + AIF No Disponible
Instrumento de Financiamiento
Monto a título de donación 5.52
Costo total del proyecto** 5.52

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de mayo de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de mayo de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2014-05-09
Project Management Moderately Satisfactory 2014-05-09
Monitoring and Evaluation Moderately Satisfactory 2014-05-09
Counterpart Funding Moderately Satisfactory 2014-05-09
Overall Low 2014-05-09
Overall Implementation Progress (IP) Satisfactory 2014-05-09

CALIFICACIONES DE LA TERMINACIÓN

No hay datos disponibles.

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

No hay datos disponibles.

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Sale of compostValor0.0019.6558.86
    Fecha1 de noviembre de 200531 de diciembre de 201231 de diciembre de 2017
    ComentarStarting date of the project activityThe figure was calculated based on the number of actual commercial sales (excluding promotional sales) compared with the availablecompost between January 1 to December 31, 2012.

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • REgistration at UNFCCC in 2010ValorNoYes
    Fecha5 de noviembre de 20055 de abril de 201031 de diciembre de 2017