Skip to Main Navigation

Coastal Cities Pollution Control Project 2

Resumen*

The objectives of the Second Coastal Cities Pollution Control Project are: (i) to improve the provision of efficient and sustainable wastewater services in participating coastal municipalities; and (ii) to reduce the nutrient load entering Croatia's coastal waters from, and pilot innovative 'wastewater treatment solutions in, selected municipalities. There are three components to the project. The first component of the project is wastewater investments...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

To improve the provision of efficient and sustainable wastewater services in participating coastal municipalities; and to reduce the nutrient load entering Croatia's coastal waters from, and pilot innovative wastewater treatment solutions in, selected municipalities.

Llave Detalles

Proyecto Detalles

  • P102732

  • Closed

  • Stjepan Gabric

  • Hrvatske Vode

  • Croacia

  • 11 de marzo de 2008

  • (a partir de la presentación ante el Directorio)

    11 de diciembre de 2008

  • 4 de junio de 2009

  • US$ 175.00 millones

  • HRVATSKE VODE

  • Europa y Asia central

  • 2009

  • US$ 87.50 millones

  • F

  • No aplicable

  • 31 de mayo de 2016

  • BANK APPROVED

  • 12 de octubre de 2023

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
International Bank for Reconstruction and Development 87.50
Borrower/Recipient 87.50

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF 87.50
Compromiso de la AIF No Disponible
Compromiso del BIRF + AIF 87.50
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 175.00

Resumen del financiamiento del Banco Mundial (millones de US$) al 30 de abril de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 30 de abril de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Counterpart Funding Satisfactory 2016-05-30
Project Management Satisfactory 2016-05-30
Overall Implementation Progress (IP) Satisfactory 2016-05-30
Progress towards achievement of PDO Moderately Satisfactory 2016-05-30
Procurement Satisfactory 2016-05-30
Financial Management Satisfactory 2016-05-30
Monitoring and Evaluation Satisfactory 2016-05-30

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 11-30-2016
ResultadosSubstantial
Riesgo para los resultados de desarrolloNegligible
Desempeño del BancoSubstantial
Desempeño del prestatarioSubstantial
Desempeño del GobiernoSubstantial
Organismo EjecutorSubstantial

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 04-20-2017INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO:
Calificación De Los ResultadosSatisfactory N/a
Riesgo Para Los Resultados De DesarrolloNegligibleN/a
Desempeño Del BancoModerately SatisfactoryN/a
Desempeño Del PrestatarioModerately SatisfactoryN/a
Desempeño Del GobiernoModerately SatisfactoryN/a
Organismo EjecutorSatisfactoryN/a
Calidad Del IfeSubstantialN/a
Calidad De SyeSubstantialN/a

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Percentage of samples from bathing areas in participating municipalities complying with applicable seawater quality standardsValor98.00100.00100.00
    Fecha16 de junio de 200911 de diciembre de 201531 de diciembre de 2015
    Comentar
  • Percentage of households in participating cities able to connect to wastewater services (average of sub-projects)Valor26.0072.0076.00
    Fecha16 de junio de 200918 de abril de 201531 de diciembre de 2015
    Comentar
  • Percentage of wastewater collected that is treated as per applicable legislation (average of sub-projects)Valor10.0048.0071.00
    Fecha16 de junio de 200918 de abril de 201531 de mayo de 2016
    Comentar
  • Performance of participating MWSCs - operating ratio (expenses/revenues) (average)Valor1.130.781.00
    Fecha16 de junio de 200918 de abril de 201531 de diciembre de 2015
    Comentar
  • Performance of participating MWSCs - collection rate (average)Valor76.0085.0086.00
    Fecha16 de junio de 200918 de abril de 201531 de diciembre de 2015
    Comentar
  • Performance of participating MWSCs - debt service ratio (average)Valor5.612.001.50
    Fecha16 de junio de 200918 de abril de 201531 de diciembre de 2015
    Comentar

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Voume(mass) of COD pollution load reduction achieved under the projectValor0.00281.00130.00
    Fecha16 de junio de 200918 de abril de 201531 de mayo de 2016
    Comentar
  • Component 1: Number of sub-loan agreements signed in participating citiesValor0.0023.0021.00
    Fecha16 de junio de 200910 de diciembre de 201531 de mayo de 2016
    Comentar
  • Reduction in pollution and nutrient load in cities with enhanced nutrient reduction facilities (BOD, N, P)Valor0%050%
    Fecha16 de junio de 200918 de abril de 201531 de mayo de 2016
    Comentar
  • Component 1: Km of wastewater collection systems constructedValor0.00162.00150.00
    Fecha16 de junio de 200910 de diciembre de 201531 de diciembre de 2015
    Comentar
  • Increased knowledge of alternative nutrient reduction wastewater treatment technologiesValor013
    Fecha16 de junio de 200918 de abril de 201531 de mayo de 2016
    Comentar
  • Component 1: Number of wastewater treatment plants commissionedValor0.0014.0018.00
    Fecha16 de junio de 200910 de diciembre de 201531 de mayo de 2016
    Comentar
  • Component 1: Number of submarine outfalls constructedValor0.0012.0012.00
    Fecha16 de junio de 200910 de diciembre de 201531 de diciembre de 2015
    Comentar
  • Component 1: Number of enhanced nutrient reduction plants commissionedValor003
    Fecha16 de junio de 200918 de abril de 201531 de mayo de 2016
    Comentar
  • (revised 4/3/12) Component 2: HV and municipalities prepare projects to EU for financingValor0.005.004.00
    Fecha16 de junio de 200910 de diciembre de 201531 de mayo de 2016
    Comentar
  • Component 2: Monitoring and benchmarking system is designed and operationalValorNoyesYes
    Fecha16 de junio de 200910 de diciembre de 201531 de diciembre de 2015
    Comentar
  • Component 3: Number of participating cities in which seawater quality monitoring system operational and baseline indicators in place prior to completion of constructionValor0.0022.0021.00
    Fecha16 de junio de 200910 de diciembre de 201531 de diciembre de 2015
    Comentar