Skip to Main Navigation

AR SOC&FISC NTL ID SYS II

Resumen*

The objective of the Second Social and Fiscal National Identification System (SINTyS) Project is to identify social or fiscal attributes of physical and legal persons in Argentina, through a sustainable information exchange system, aimed at improving the efficiency, effectiveness, and impact of social services and fiscal programs at all levels of government in Argentina. There are five components to the project. The first component is the institutional...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

The project's development objective is to identify social and/or fiscal attributes of physical and legal persons in Argentina, through a sustainable information exchange system, aimed at improving the efficiency, effectiveness, and impact of social services and fiscal programs at all levels of government in Argentina. The specific objectives to be pursued under this operation are: 1. to expand and consolidate the network underlying the exchange of social and fiscal information among public agencies at the national, provincial, and municipal levels of government, with provisions to ensure data protection, accessibility, and the quality and accuracy of information; and 2. to consolidate the institutionalization of SINTyS as an independent national entity responsible for coordinating and setting standards governing the exchange of information within Argentina's public sector.

Llave Detalles

Proyecto Detalles

  • P101171

  • Closed

  • Henry Forero Ramirez

  • N/A

  • Argentina

  • 6 de febrero de 2008

  • (a partir de la presentación ante el Directorio)

    10 de julio de 2008

  • 27 de febrero de 2009

  • US$ 20.00 millones

  • C

  • No aplicable

  • 31 de diciembre de 2013

  • BANK APPROVED

  • 15 de marzo de 2013

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
Borrower/Recipient 8.03
International Bank for Reconstruction and Development 20.00

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF 20.00
Compromiso de la AIF No Disponible
Compromiso del BIRF + AIF 20.00
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 28.03

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de julio de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de julio de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Counterpart Funding Satisfactory 2013-12-31
Financial Management Satisfactory 2013-12-31
Overall Implementation Progress (IP) Satisfactory 2013-12-31
Progress towards achievement of PDO Moderately Satisfactory 2013-12-31
Procurement Moderately Satisfactory 2013-12-31
Project Management Satisfactory 2013-12-31
Monitoring and Evaluation Satisfactory 2013-12-31

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 06-19-2014
Resultados
Riesgo para los resultados de desarrolloSubstantial
Desempeño del Banco
Desempeño del prestatario
Desempeño del Gobierno
Organismo Ejecutor

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 04-14-2015INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO:
Calificación De Los ResultadosModerately Satisfactory N/a
Riesgo Para Los Resultados De DesarrolloModerateN/a
Desempeño Del BancoModerately SatisfactoryN/a
Desempeño Del PrestatarioModerately SatisfactoryN/a
Desempeño Del GobiernoModerately SatisfactoryN/a
Organismo EjecutorModerately SatisfactoryN/a
Calidad Del IfeSatisfactoryN/a
Calidad De SyeSubstantialN/a

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Amount of incorrect benefits not awarded due to SINTyS in a given year (in US$ Million)Valor0 millionActual numbers not yet available.51 million
    Fecha12 de junio de 20084 de diciembre de 201331 de diciembre de 2013
    ComentarThe new impact tool is being implemented.
  • Increase in tax collections due to SINTyS in a given year (in US$ Million)Valor0 millionActual numbers not yet available.2.6 million
    Fecha12 de junio de 20084 de diciembre de 201331 de diciembre de 2013
    ComentarThe new impact tool is being implemented.
  • The information exchange network mantains current availability (as percent)(Text Description)Valor97.0097.0097.00
    Fecha30 de septiembre de 201331 de diciembre de 2013
    ComentarAchieved.
  • The number of data types for which SINTyS and ONTI have issued information-exchange standards has increased from 0 to 50.Valor0.000.0050.00
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    Comentar
  • The number of government agencies and programs using consistent common processes to identify entities and assets has increasedValor1610538
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarOver-achieved
  • The percentage of physical persons that can be identified univocally by SINTyS has increasedValor31 percent92 percent92 percent
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarAchieved
  • The percentage of the juridical persons univocally identified has increasedValor41 percent60 percent70 percent
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarAbove Year 4 target
  • The population identified with family relationship data has increased (as percent)Valor9 percent32 percent32 percent
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarAchieved
  • Population identified with a level of confidence equal or greater than 75 percent has increased (in million)Valor35.2 million39 million38.2 million
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarOver-achieved
  • The number of "highly critical" vulnerabilities exploited by penetration test activities simulating a legitimate SINTyS user has decreasedValor2PWC conducted a first pentest in the second semest0
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarHighly critical vulnerabilities are measured by service.

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • SINTyS advisory body in place, with representation from key agencies at the national level (DNPDP, ONTI, RENAPER, AFIP, AN SES), and meets regularly (Text Description) - Custom IndicatorValorIt does not formally existCNPS monthly meetingsCNPS monthly meetings (recurrent)
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarAchieved.
  • Provincial advisory body in place, with representation from provincial authorities, and meets regularly(Text Description) - Custom IndicatorValorIt does not formally existAnnual meetings with provincial coordinators.Annual meetings with provincial coordinators (recu
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarAchieved.
  • An M&E system with a focus on, among others, information exchanges, data quality, technological framework, security, a nd overall performance, is in place (Text Description)ValorIt does not existA progress report with key management indicators iMonthly progress report with key management indica
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarAchieved.
  • SINTyS' systems are audited regularly by a qualified external auditor(Text Description) - Custom IndicatorValorOnce a yearThe Internal Control Office (SIGEN) and the GeneraOnce a year
    Fecha30 de septiembre de 201331 de diciembre de 2013
    ComentarThe perimetral audit that will be undertaken by PWC is currently taking shape.
  • A formal mechanism has been established that allows individual citizens to verify the accuracy of their personal information and incase of errors, correct it.ValorNo formal mechanism is now in placeAchieved. Information on which agencies to approaSINTyS informs in its website to which agency the
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarSINTyS cannot grant access to individual citizens as it is not the owner of the information. However, as part of the MTR and theproposed restructuring, it was agreed that SINTyS will inform in its website to which agency the citizen need to go in case oferrors by theme.
  • The number of municipalities that routinely exchange information under SINTyS has increasedValor1142126
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarNot likely to be achieved.
  • The benefits from the exchange of fiscal and social information by subnational governments have increased (in US$ million)Valor233Actual numbers not yet available.473
    Fecha12 de junio de 20084 de diciembre de 201331 de diciembre de 2013
    ComentarThe new tool to calculate impact is being implemented.
  • The number of provinces in which the registries of physical persons (registros civiles) have information in electronic for m has increasedValor131722
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarPartially achieved.
  • The percentage of overall information from registries of physical persons that is available in electronic form has increas ed (as percent)Valor31%75%92%
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarPartially achieved.
  • The number of provinces in which registries of juridical persons (registros de personas juridicas) have information in electronic form has increasedValor61218
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    Comentar
  • The number of provinces where the registries of deeds (registros de propiedad) have information in electronic form has inc reased from 10 to 20Valor101720
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarAbove year 4 target
  • The percentage of overall information from registries of deeds that is available in electronic form has increased (as perc ent)Valor618085
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarAbove Year 4 target
  • The number of government agencies utilizing Web services for data entry (such as prefilling of data fields) has increasedValor79140
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarOver-achieved
  • An information management framework that includes, among others, decentralized data quality management (Stage III) has bee n approvedValornot in placeAssessment report and capacity building strategy
    Fecha12 de junio de 200813 de junio de 201331 de diciembre de 2013
    ComentarNew applications allow for direct exchanges.
  • Guarantee at least 99 percent up time of the network (as percent)Valor0Highavailability on the DB99
    Fecha12 de junio de 200813 de junio de 201331 de diciembre de 2013
    Comentar
  • A secure data center and control center are imlemented(Text Description) - Custom IndicatorValorNot in placeCenter in operation.Center in operation
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarAchieved.
  • DNPDP is formally involved in validating access rights to information (access profiles) and the use of SWEDValorConversations with DNPDP about access profilesThe document with profiles and draft laws have beeAccess profiles and use of services (and any modif
    Fecha30 de abril de 201130 de septiembre de 201331 de diciembre de 2013
    Comentar
  • Number of national and provincial nodes connected and in operation. Number of institutions on Stage III and number of municipal offices in operation.Valor6 SPFO nodes connected, 7 in process, no municipal18 national nodes, 3 in the proess of being instalInformation management framework in place
    Fecha30 de septiembre de 201331 de diciembre de 2013
    Comentar
  • Percentage on compliance with the minimum and desirable quality standards of the databases received from provincial and municipal agenciesValor50.0075.0075.00
    Fecha30 de abril de 201130 de septiembre de 201331 de diciembre de 2013
    ComentarAchieved.
  • Percentage of capacity building in Quality of Data in the provincial nodes to enhance capacities towards decentralizationValor30.0069.0070.00
    Fecha30 de abril de 201130 de septiembre de 201331 de diciembre de 2013
    ComentarAlmost achieved (Target 70%)
  • Number of national agencies implementing national information exchange standardsValor2.008.004.00
    Fecha30 de abril de 201130 de septiembre de 201331 de diciembre de 2013
    ComentarOver-achieved.
  • Number of provincial agencies implementing national information exchange standardsValor4.0011.007.00
    Fecha30 de abril de 201130 de septiembre de 201331 de diciembre de 2013
    ComentarOver-achieved.
  • The number of provinces that are financing the salary of the SINTyS Provincial Coordinator has increasedValor41212
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarAchieved.
  • The number of provinces that have established their provincial coordinating units has increasedValor132124
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarPartially achieved.
  • The number of provincial agencies that routinely exchange information under SINTyS has increasedValor639892
    Fecha12 de junio de 200830 de septiembre de 201331 de diciembre de 2013
    ComentarOver-achieved