Integrated Coastal Zone Management

Resumen*

The objective of the Integrated Coastal Zone Management (ICZM) Project is to assist Government of India (GoI) in building national capacity for implementation of comprehensive coastal management approach in the country, and piloting the integrated coastal zone management approach in states of Gujarat, Orissa and West Bengal. There are four components to the project, the first component being national ICZM capacity building. The national component...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

The project development objective is to assist GoI in building national capacity for implementation of comprehensive coastalmanagement approach in the country, and piloting the integrated coastal zone management approach in states of Gujarat, Orissa and West Bengal.

Llave Detalles

Proyecto Detalles

  • P097985

  • Closed

  • Milen Dyoulgerov Vollen , Sitarama Krishna Addepalli

  • The Republic of India

  • India

  • 26 de febrero de 2007

  • (a partir de la presentación ante el Directorio)

    15 de junio de 2010

  • 12 de agosto de 2008

  • US$ 285.67 millones

  • Society of Integrated Coastal Management

  • Asia meridional

  • 2010

  • US$ 221.96 millones

  • A

  • 8 de julio de 2024

  • 30 de junio de 2020

  • BANK APPROVED

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
Borrower/Recipient 63.71
IDA Credit 221.96

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF No Disponible
Compromiso de la AIF 221.96
Compromiso del BIRF + AIF 221.96
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 285.67

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Counterpart Funding Satisfactory 2020-06-29
Project Management Satisfactory 2020-06-29
Financial Management Satisfactory 2020-06-29
Overall Safeguards Rating Satisfactory 2020-06-29
Progress towards achievement of PDO Highly Satisfactory 2020-06-29
Monitoring and Evaluation Highly Satisfactory 2020-06-29
Overall Implementation Progress (IP) Highly Satisfactory 2020-06-29
Procurement Satisfactory 2020-06-29
Overall Safeguards Rating Satisfactory 2020-06-29

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 12-21-2020
ResultadosSubstantial
Riesgo para los resultados de desarrollo
Desempeño del BancoSubstantial
Desempeño del prestatario
Desempeño del Gobierno
Organismo Ejecutor

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 06-04-2021INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO:
Calificación De Los ResultadosSatisfactory N/a
Riesgo Para Los Resultados De DesarrolloN/a
Desempeño Del BancoModerately SatisfactoryN/a
Desempeño Del PrestatarioN/a
Desempeño Del GobiernoNot RatedN/a
Organismo EjecutorN/a
Calidad Del IfeSubstantialN/a
Calidad De SyeSubstantialN/a

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Direct project beneficiariesValor0.0017803373.0011000000.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Female beneficiariesValor0.0050.000.00
    Fecha15 de diciembre de 20101 de junio de 2018
    Comentar
  • National and State level technical capacity established for ICZM planning with supporting technical staffing according to defined criteriaValorNoYesYes
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Implementation of demonstrable ICZM pilot activities carried outValorNoYesYes
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Knowledge and planning base in integrated coastal zone management established according to defined criteriaValorNoYesYes
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Institutional structure at National, and State level supportive of integrated coastal zone management established according to defined criteriaValorNoYesYes
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Kilometer of mainland coastline for which coastal sediment cell, hazard line and ecologically sensitive areas are mapped and delineatedValor0.005500.005500.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Pilot investment projects in Gujarat ICZMValor0.005.006.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Skilled staff in ICZM planning and implementation in Odisha StateValor0.0017.0020.00
    Fecha15 de junio de 201530 de junio de 202029 de diciembre de 2017
    Comentar
  • Pilot investment projects in West BengalValor0.0010.0010.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • ICZM knowledge outputs generated by National Center for Sustainable Coastal ManagementValor0.00109.0013.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Area restored or re/afforestedValor0.0019503.0012000.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Pilot investment projects in OdishaValor0.009.0010.00
    Fecha15 de junio de 201026 de septiembre de 201929 de diciembre de 2017
    Comentar
  • Skilled staff in ICZM planning and implementation in West Bengal StateValor0.008.0015.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Skilled staff in ICZM planning and implementation at National levelValor10.00117.0075.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Coastline and freshwater under biodiversity protection (km)Valor0.00196.00400.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • ICZM plan for West Bengal Coast prepared using the designed participatory process, and submitted for approval by Government of WestBengalValor0.001.001.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • Area re/afforestedValor0.0016000.0012000.00
    Fecha15 de junio de 201530 de junio de 202029 de diciembre de 2017
    Comentar
  • Plan for institutional structure at National, and State level supportive of integrated coastal zone management prepared and submitted to Government for approvalValorNoNoYes
    Fecha15 de junio de 201030 de junio de 202015 de diciembre de 2015
    Comentar
  • Industrial and municipal waste disposal capacity created under the projectValor0.0071.0080.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • ICZM plan for Paradip-Dhamra and Gopalpur-Chilika prepared using the designed participatory process, and submitted to approval by Government of OdishaValor0.001.001.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • ’Skilled staff in ICZM planning and implementation in Gujarat StateValor0.0015.0020.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar
  • ICZM plan for Gulf of Kachchh prepared using the designed participatory process, and submitted for approval to Government of GujaratValor0.001.001.00
    Fecha15 de junio de 201030 de junio de 202029 de diciembre de 2017
    Comentar