Entidad De Financiamiento | Compromisos |
---|---|
Borrower/Recipient | 110.10 |
International Bank for Reconstruction and Development | 42.00 |
P089866
Closed
David Reinstein
N/A
10 de julio de 2007
(a partir de la presentación ante el Directorio)
20 de mayo de 2008
18 de junio de 2009
US$ 152.10 millones
N/A
2008
US$ 42.00 millones
B
No aplicable
30 de septiembre de 2013
BANK APPROVED
1 de noviembre de 2023
Entidad De Financiamiento | Compromisos |
---|---|
Borrower/Recipient | 110.10 |
International Bank for Reconstruction and Development | 42.00 |
Línea de productos | BIRF/AIF |
---|---|
Compromiso del BIRF | 42.00 |
Compromiso de la AIF | No Disponible |
Compromiso del BIRF + AIF | 42.00 |
Instrumento de Financiamiento | |
---|---|
Monto a título de donación | No Disponible |
Costo total del proyecto** | 152.10 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2013-10-11 |
Overall Safeguards Rating | Satisfactory | 2013-10-11 |
Progress towards achievement of PDO | Satisfactory | 2013-10-11 |
Procurement | Satisfactory | 2013-10-11 |
Financial Management | Satisfactory | 2013-10-11 |
Overall Safeguards Rating | Satisfactory | 2013-10-11 |
Counterpart Funding | Satisfactory | 2013-10-11 |
Project Management | Satisfactory | 2013-10-11 |
Monitoring and Evaluation | Satisfactory | 2013-10-11 |
INDICADOR | INFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 03-28-2014 |
---|---|
Resultados | Moderately Satisfactory |
Riesgo para los resultados de desarrollo | Modest |
Desempeño del Banco | Moderately Satisfactory |
Desempeño del prestatario | Moderately Satisfactory |
Desempeño del Gobierno | Moderately Unsatisfactory |
Organismo Ejecutor | Substantial |
INDICADOR | REVISIÓN DEL ICR: 10-30-2015 | INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO: |
---|---|---|
Calificación De Los Resultados | Moderately Satisfactory | N/a |
Riesgo Para Los Resultados De Desarrollo | Significant | N/a |
Desempeño Del Banco | Moderately Satisfactory | N/a |
Desempeño Del Prestatario | Moderately Satisfactory | N/a |
Desempeño Del Gobierno | Moderately Satisfactory | N/a |
Organismo Ejecutor | Moderately Satisfactory | N/a |
Calidad Del Ife | Satisfactory | N/a |
Calidad De Sye | Negligible | N/a |
INDICATOR | LÍNEA DE REFERENCIA | EN CURSO | OBJETIVO |
---|
CRI's per company (EdeNorte, EdeSur, EdeEste) | Valor | EdeNorte: 63%EdeSur: 53%EdeEste: 62% | EdeNorte: 61.9%EdeSur: 68.2%EdeEste: 59. | EdeNorte: 71%EdeSur: 75%EdeEste: 75% |
Fecha | 31 de diciembre de 2010 | 31 de mayo de 2013 | 30 de septiembre de 2013 | |
Comentar | It was revealed that the three separate regions were regulated under different tariff structures and therefore required differentbaselines for the project monitoring indicators, therefore the project is using the adjusted Dec 2010 figures as a baseline.CRIformula = (energy billed by distribution companies / energy purchased by distribution companies) multiplied by (electricitybillings paid by consumers / total electricity billings issued to consumers). | Data used to calculate this indicator has been extracted from CDEEE monthly report of May 2013 (latest data available). | CRI cumulative six months. |
Average service availability index (ASAI) per circuits with project investments and in each EDE as whole | Valor | EdeNorte: 73%EdeSur: 74%EdeEste: 75% | EdeEste: 75.0% | 75% |
Fecha | 31 de diciembre de 2007 | 30 de junio de 2013 | 30 de septiembre de 2013 | |
Comentar | 1st Quarter 2007 Baseline (SIE Indicadores Calidad del Servicio 2007). Numbers in percentage represent ASAI for EDE as a whole.(ASAI) is the ratio of the total number of customer hours that service was available during a given time period to the totalcustomer hours demanded. | Data based on CDEEE's trimester reporting as of June, 2013. New data for EdeSur and EdeNorte were not reported. |
Percentage of people satisfied with electricity service by distribution company | Valor | 62% | 75% | |
Fecha | 31 de diciembre de 2007 | 31 de julio de 2013 | 30 de septiembre de 2013 | |
Comentar | Percentage | New data were not reported on percentages. |
People provided with access to electricity by household connections | Valor | 0.00 | 107531.00 | 81429.00 |
Fecha | 31 de diciembre de 2010 | 3 de septiembre de 2013 | 30 de septiembre de 2013 | |
Comentar | EDESUR: 38,979EDENORTE: 33,907 EDEESTE: 33,645 | EDESUR: 31,583EDENORTE: 24,964 EDEESTE: 24,942 |
Ppl provided wth elec. by hhold conn.–Offgrid/minigrid–Only renewable sources | Valor | 0.00 | 107531.00 | 81429.00 |
Fecha | 31 de diciembre de 2010 | 3 de septiembre de 2013 | 30 de septiembre de 2013 | |
Comentar |
NUmber of new connections (customers) | Valor | 0.00 | 107531.00 | 81429.00 |
Fecha | 31 de diciembre de 2010 | 3 de septiembre de 2013 | 30 de septiembre de 2013 | |
Comentar |
INDICATOR | LÍNEA DE REFERENCIA | EN CURSO | OBJETIVO |
---|
Rehabilitation of selected circuits | Valor | No rehabilitation of circuits | EdeNorte (5)EdeSur (6) EdeEste (4) | EdeNorte (5) EdeSur (12) EdeEste (18) |
Fecha | 31 de diciembre de 2010 | 31 de julio de 2013 | 30 de septiembre de 2013 | |
Comentar | Data as of end of July 2013. | They will not reach targets in number of circuits but will be above targets on number of of new customers, or installations. Theexplanation is that the project initiated without a reliable data base and without detailed engineering per circuit. |
CRIs of rehabilitated circuits | Valor | Baseline varies according to each specific circuit | EdeNorte:LVEG103: 75%LVEG105: 64%VVAS101: 80%C | The target value varies according to each specific |
Fecha | 31 de diciembre de 2007 | 31 de julio de 2013 | 30 de septiembre de 2013 | |
Comentar | CRI formula = (energy billed by distribution companies / energy purchased by distribution companies) multiplied by (electricitybillings paid by consumers / total electricity billings issued to consumers). | Data based on CDEEE's monthly reporting as of July, 2013. |
Increased average availability index (ASAI) | Valor | Baseline varies according to each specific circuit | EdeEste: 75% (June 2013)EdeSur: 73% (July 2013) | 87% for all three EDE's. It is unlikely they reach |
Fecha | 31 de diciembre de 2010 | 31 de julio de 2013 | 30 de septiembre de 2013 | |
Comentar | (ASAI) is the ratio of the total number of customer hours that service was available during a given time period to the totalcustomer hours demanded. | Data reported by CDEEE as June and July 2013. No more recent data available. |
Operating costs of the EDEs | Valor | Total EDEs operating costs: US$226 millionEdeNort | There is no target because the indicator was desig | |
Fecha | 31 de enero de 2010 | 26 de diciembre de 2012 | 30 de septiembre de 2013 | |
Comentar | 2007 baseline: audited TOC, and VE (CDEEE report on operational expenditures). | Data reported by CDEEE as of September 2012. This data needs to be verified with the Annual Audited Report to be delivered inMarch2013 as well as with the ongoing independent audit | TOCi < TOCi-1xK(Audited Report on Operational Expenditures using formula). |