Skip to Main Navigation

Secondary Education Development and Girls Access Program

Resumen*

The objective of the Secondary Education Development and Girls Access Project is to support the Government of Yemen's program for improving gender equity, quality, and efficiency of secondary education in selected districts with a particular focus on girls in rural areas. The first project components is to improving equity and reducing gender gaps through demand and supply-side interventions by: (i) upgrading and furnishing school facilities; (ii)...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

To improve gender equity, quality, and efficiency of secondary education in selected districts with a particular focus on girls in rural areas.

Llave Detalles

Proyecto Detalles

  • P089761

  • Closed

  • Tomomi Miyajima

  • Ministry of Planning and International Cooperation

  • Yemen, República del

  • 21 de noviembre de 2006

  • (a partir de la presentación ante el Directorio)

    18 de marzo de 2008

  • 6 de enero de 2009

  • US$ 41.50 millones

  • B

  • No aplicable

  • 31 de mayo de 2015

  • BANK APPROVED

  • 16 de julio de 2024

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
UK: British Department for International Development (DFID) 2.40
GERMANY: German Technical Assistance Corporation (GTZ) 3.00
NETHERLANDS: Min. of Foreign Affairs / Min. of Dev. Coop. 6.60
IDA Credit 20.00
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) 9.50
Borrower/Recipient 8.70

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF No Disponible
Compromiso de la AIF 20.00
Compromiso del BIRF + AIF 20.00
Instrumento de Financiamiento
Monto a título de donación 21.50
Costo total del proyecto** 50.20

Resumen del financiamiento del Banco Mundial (millones de US$) al 30 de abril de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 30 de abril de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Project Management Moderately Satisfactory 2015-05-31
Progress towards achievement of PDO Moderately Satisfactory 2015-05-31
Financial Management Moderately Satisfactory 2015-05-31
Monitoring and Evaluation Moderately Satisfactory 2015-05-31
Overall Safeguards Rating Moderately Satisfactory 2015-05-31
Overall Safeguards Rating Moderately Satisfactory 2015-05-31
Procurement Moderately Satisfactory 2015-05-31
Counterpart Funding Moderately Unsatisfactory 2015-05-31
Overall Implementation Progress (IP) Moderately Unsatisfactory 2015-05-31

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 12-17-2015
ResultadosModerately Satisfactory
Riesgo para los resultados de desarrolloHigh
Desempeño del BancoModerately Satisfactory
Desempeño del prestatarioModerately Satisfactory
Desempeño del GobiernoModerately Satisfactory
Organismo EjecutorSubstantial

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 09-21-2016INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO:
Calificación De Los ResultadosModerately Satisfactory N/a
Riesgo Para Los Resultados De DesarrolloHighN/a
Desempeño Del BancoModerately SatisfactoryN/a
Desempeño Del PrestatarioModerately SatisfactoryN/a
Desempeño Del GobiernoModerately UnsatisfactoryN/a
Organismo EjecutorSatisfactoryN/a
Calidad Del IfeSubstantialN/a
Calidad De SyeModestN/a

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Gender parity index in student enrollment in the intervention governoratesValor0.43to be updated once the AES data is processed0.60
    Fecha19 de febrero de 200815 de mayo de 201515 de mayo de 2015
    Comentar
  • G10 to G12 male retention rate in the intervention districtsValor73.0to be updated once the AES data is processed for t81.0
    Fecha19 de febrero de 200815 de mayo de 201531 de mayo de 2015
    Comentar
  • G10 to G12 female retention rate in the intervention districtsValor78.3to be updated once the AES data for this indicator84.3
    Fecha19 de febrero de 200815 de mayo de 201531 de mayo de 2015
    Comentar
  • Average score in mathematics and science tests for G11 studentsValor19.3End line survey for this indicator was aborted due40
    Fecha9 de febrero de 200915 de mayo de 201531 de mayo de 2015
    Comentar

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Civil works programs (including civil works, furniture, and equipments) completed in 44 schools.ValorNA4244 schools
    Fecha19 de febrero de 200815 de mayo de 201531 de mayo de 2015
    Comentar
  • 5,200 students attending the project schools using the transportation scheme provided by the School Community Grant.Valor081415200
    Fecha19 de febrero de 200815 de mayo de 201531 de mayo de 2015
    Comentar
  • 89 female staff financed through the School Community GrantValor08989 female staff.
    Fecha19 de febrero de 200815 de mayo de 201531 de mayo de 2015
    Comentar
  • Number of schools with science labsValor0.0050.0050.00
    Fecha5 de abril de 201215 de mayo de 201531 de mayo de 2015
    Comentar
  • Number of schools equipped with computer labsValor0.0050.0050.00
    Fecha5 de abril de 201215 de mayo de 201531 de mayo de 2015
    Comentar
  • Number of schools equipped with librariesValor0.0050.0050.00
    Fecha5 de abril de 201215 de mayo de 201531 de mayo de 2015
    Comentar
  • Number of teachers trained in subject modules in 5 governoratesValor0.0014349.0017267.00
    Fecha5 de abril de 201215 de mayo de 201531 de mayo de 2015
    Comentar
  • Number of teachers from 44 schools trained on pedagology training certificationValor0This activity is put on hold due to suspension of 1500
    Fecha5 de abril de 201215 de mayo de 201531 de mayo de 2015
    Comentar
  • Average performance of teachers from the 44 schools in classroom observation testValor54.8Consultancy was carried out by ERDC, yet the activ70
    Fecha5 de abril de 201215 de mayo de 201531 de mayo de 2015
    Comentar