Resumen*

This is the Second School Access and Improvement Program Project, and will continue to support classroom expansion, but with greater attention paid to middle school construction and equipment. The demand for middle school places is expected to increase sharply by 2006-2007, and it is expected the additional classrooms will accommodate the increased flow of students from primary through the middle school cycle. The project will also expand coverage...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

The project (Phase II of the APL) will increase access to basic education equitably, improve the quality of education and increase the efficiency of the education system.

Llave Detalles

Proyecto Detalles

  • P086994

  • Closed

  • Christina D. Wright

  • N/A

  • Djibouti

  • 7 de junio de 2004

  • (a partir de la presentación ante el Directorio)

    8 de noviembre de 2005

  • 26 de marzo de 2006

  • US$ 10.00 millones

  • B

  • No aplicable

  • 31 de diciembre de 2011

  • BANK APPROVED

  • 16 de julio de 2024

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
IDA Credit 10.00
Borrower/Recipient 1.00

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF No Disponible
Compromiso de la AIF 10.00
Compromiso del BIRF + AIF 10.00
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 11.00

Resumen del financiamiento del Banco Mundial (millones de US$) al 30 de abril de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 30 de abril de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Counterpart Funding Moderately Satisfactory 2011-11-04
Project Management Moderately Satisfactory 2011-11-04
Overall Implementation Progress (IP) Moderately Satisfactory 2011-11-04
Progress towards achievement of PDO Moderately Satisfactory 2011-11-04
Procurement Moderately Satisfactory 2011-11-04
Financial Management Moderately Satisfactory 2011-11-04
Monitoring and Evaluation Moderately Unsatisfactory 2011-11-04
Overall Safeguards Rating Satisfactory 2011-11-04
Overall Safeguards Rating Satisfactory 2011-11-04

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 06-21-2012
ResultadosModerately Satisfactory
Riesgo para los resultados de desarrolloModest
Desempeño del BancoModerately Satisfactory
Desempeño del prestatarioModerately Satisfactory
Desempeño del GobiernoModerately Satisfactory
Organismo EjecutorModerately Satisfactory

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 01-24-2013INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO:
Calificación De Los ResultadosModerately Unsatisfactory N/a
Riesgo Para Los Resultados De DesarrolloModerateN/a
Desempeño Del BancoModerately SatisfactoryN/a
Desempeño Del PrestatarioModerately UnsatisfactoryN/a
Desempeño Del GobiernoModerately UnsatisfactoryN/a
Organismo EjecutorModerately UnsatisfactoryN/a
Calidad Del IfeSatisfactoryN/a
Calidad De SyeNegligibleN/a

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • GER ratio girls to boys will go from .55 to .70Valor.55.77
    Fecha11 de febrero de 20057 de mayo de 201031 de diciembre de 2011
    Comentar
  • Percentage of children completing primary schooling without repeating increases from 53% to 83%, of which girls from 50% to 83%. [NUMBERS ARE BEING REVIEWED]Valor39%, (25% for girls)80.0% (78% for girls)83%, of which girls 83% at end of project.
    Fecha11 de febrero de 20057 de mayo de 200931 de diciembre de 2011
    Comentardata is from academic year 2008/2009
  • Primary cycle repetition rates drop from 10.4% to 5.4%.Valor10.4%5.4%5.4%
    Fecha11 de febrero de 20057 de mayo de 200931 de diciembre de 2011
    Comentardata is from academic year 2008/2009
  • Primary cycle drop-out rates drop from 3.4% to 1.2%.Valor3.4%1.2%1.2%
    Fecha11 de febrero de 20057 de mayo de 200930 de junio de 2009
    Comentardata is from academic year 2008/2009
  • Non-salary recurrent spending rises from 6.6% to 15.0% of total recurrent spending on primary education.Valor6.6%9.2%15.0%
    Fecha11 de febrero de 20057 de mayo de 200930 de junio de 2009
    Comentardata is from academic year 2008/2009
  • Percentage of teachers receiving continuing training rises from 30% to 90%.Valor30%87%90%
    Fecha11 de febrero de 20057 de mayo de 200930 de junio de 2009
    Comentardata is from academic year 2008/2009
  • Percentage of schools with Parent-Teacher Associations (PTAs) rises from 70% to 80%.Valor70%90%
    Fecha26 de marzo de 200616 de diciembre de 200931 de diciembre de 2010
    Comentar
  • Teacher student ratio in public primary school to increaseValor39.4041.0045.00
    Fecha18 de mayo de 200515 de mayo de 200831 de diciembre de 2010
    ComentarThis indicator was 42 in 2006 and 41 in 2007. Will be updated for the next ISR.

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Primary education textbooks in basic education subject matters have a 1:1 ratio (French, Arabic, and Mathematics) (Comp II).ValorArabic: 1:2, French: 1:1, Math: 1:2Arabic: 1:1, French: 1:1, Math: 1:1
    Fecha31 de diciembre de 201031 de diciembre de 2011
    Comentarsource: MENESUP Annual Statistics 2009-2010
  • 90% of teachers have received appropriate in-service training (Comp II).Valorless than 50 % at launch and 60% in 2005/687%90%.
    Fecha11 de febrero de 20057 de mayo de 200931 de diciembre de 2011
    Comentar
  • 80% of the training program planned for the staff of the Ministry are completed each year (Comp III).Valor0 at start of project.unknown80%
    Fecha11 de febrero de 20057 de mayo de 200931 de diciembre de 2011
    ComentarThis activity will be followed up with the ministry in early 2010 as part of the implementation of an organizational audit carriedout in 2009.
  • Total GER in primary education is 61.9% (Comp I)Valor0.000.000.00
    Fecha26 de marzo de 200616 de diciembre de 200931 de diciembre de 2010
    Comentar