Entidad De Financiamiento | Compromisos |
---|---|
IDA Credit | 3.00 |
Borrower/Recipient | 0.81 |
P083453
Closed
Liba C. Strengerowski-Feldblyum
N/A
21 de octubre de 2002
(a partir de la presentación ante el Directorio)
9 de noviembre de 2004
14 de marzo de 2005
US$ 3.81 millones
N/A
2005
US$ 3.00 millones
B
N/A
31 de marzo de 2011
BANK APPROVED
15 de enero de 2013
Entidad De Financiamiento | Compromisos |
---|---|
IDA Credit | 3.00 |
Borrower/Recipient | 0.81 |
Línea de productos | BIRF/AIF |
---|---|
Compromiso del BIRF | No Disponible |
Compromiso de la AIF | 3.00 |
Compromiso del BIRF + AIF | 3.00 |
Instrumento de Financiamiento | |
---|---|
Monto a título de donación | No Disponible |
Costo total del proyecto** | 3.81 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Unsatisfactory | 2011-03-29 |
Counterpart Funding | Satisfactory | 2011-03-29 |
Project Management | Moderately Satisfactory | 2011-03-29 |
Overall Safeguards Rating | Moderately Satisfactory | 2011-03-29 |
Progress towards achievement of PDO | Moderately Satisfactory | 2011-03-29 |
Financial Management | Moderately Satisfactory | 2011-03-29 |
Monitoring and Evaluation | Moderately Satisfactory | 2011-03-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2011-03-29 |
Overall Safeguards Rating | Moderately Satisfactory | 2011-03-29 |
INDICADOR | INFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 10-26-2011 |
---|---|
Resultados | Moderately Satisfactory |
Riesgo para los resultados de desarrollo | Modest |
Desempeño del Banco | Moderately Satisfactory |
Desempeño del prestatario | Moderately Satisfactory |
Desempeño del Gobierno | Moderately Satisfactory |
Organismo Ejecutor | Highly Satisfactory |
INDICADOR | REVISIÓN DEL ICR: 04-30-2013 | INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO: |
---|---|---|
Calificación De Los Resultados | Moderately Satisfactory | N/a |
Riesgo Para Los Resultados De Desarrollo | High | N/a |
Desempeño Del Banco | Moderately Unsatisfactory | N/a |
Desempeño Del Prestatario | Moderately Satisfactory | N/a |
Desempeño Del Gobierno | Moderately Unsatisfactory | N/a |
Organismo Ejecutor | Moderately Satisfactory | N/a |
Calidad Del Ife | Satisfactory | N/a |
Calidad De Sye | Modest | N/a |
INDICATOR | LÍNEA DE REFERENCIA | EN CURSO | OBJETIVO |
---|
METT score: Management effectiveness score of the 5 protected conservation areas (KPI) | Valor | 0.00 | 0.00 | 0.00 |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | 3,500 sq km of land and water under improved management measured through the METT | see scores in the next section.This is the KPI - the METT scores are not indicators, but a tool to measure effectiveness | end target was set at mid-term only in response to management demands, it was never part of the original M&E package for theproject in the PAD. Targets were overly ambitious. |
Sub- (micro) projects funded by FIAL satisfactorily achieved their objectives (KPI) | Valor | 0.00 | 81.30 | 75.00 |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | Data from internal evaluation from the project team |
Infringements of the applicable regulatory framework related to the Reserved Fishing Zones by fishing vessels decreased (KPI) | Valor | regulatory framework not established | 10 % decline at community level (framework adopted | No. of infringement declined by 10% |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | framework was signed on March 16, 2010 |
Government provides sufficient financial resources to cover the operational and maintenance costs of all fisheries surveillance activities, including surveillance stations (KPI) | Valor | no operational and maintenance funds | the Government has started to contribute financial | Full coverage of operational costs of project - fu |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | The Government in the last year provided what was necessary to operationalize the surveillance post of Caravela such as salariesfor staff based in Caravela, supplied the post with two vessels and funds for maintenance. |
Public or private development projects eligible for review submitted for EIA review prior to being implemented (KPI) | Valor | 0.00 | 100.00 | 100.00 |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | Instituion to conduct such reviews is being created at project start | based on data from CAIA | All eligible projects submitted for review |
Cacheu | Valor | 56.00 | 107.00 | 136.00 |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | The KPI is: 3,500 sq km of land and water under improved : the METT scores are not indicators, but a tool to measureeffectiveness. It must be noted that although the end target was not achieved, it made quantifiable progress almost at 100% (almostdoubled from the baseline). It should also be noted that when using the METT scores, progress is not Linear. | end target was set at mid-term only only in response to management demands, it was never part of the original M&E package for theproject in the PAD. Targets were overly ambitious. |
Cantanhez | Valor | 40.00 | 56.00 | 70.00 |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | The KPI is: 3,500 sq km of land and water under improved : the METT scores are not indicators, but a tool to measureeffectiveness. It must be noted that although the end target was not achieved, it made quantifiable progress for a Park that wasestablished during the project's tenure | end target was set at mid-term only only in response to management demands, it was never part of the original M&E package for theproject in the PAD. Targets were overly |
Cufada | Valor | 54.00 | 75.00 | 70.00 |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | although end targets were overly ambitious, Cufada managed to surpass the target value | end target was set at mid-term only only in response to management demands, it was never part of the original M&E package for theproject in the PAD. Targets were overly ambitious. |
Joao Vieira | Valor | 65.00 | 105.00 | 139.00 |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | The KPI is: 3,500 sq km of land and water under improved : the METT scores are not indicators, but a tool to measureeffectiveness. It must be noted that although the end target was not achieved, it made quantifiable progress almost at 100% (almostdoubled from the baseline).It should also be noted that when using the METT scores, progress is not Linear. | end target was set at mid-term only only in response to management demands, it was never part of the original M&E package for theproject in the PAD. Targets were overly ambitious. |
Orango | Valor | 63.00 | 114.00 | 139.00 |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | The KPI is: 3,500 sq km of land and water under improved : the METT scores are not indicators, but a tool to measureeffectiveness. It must be noted that although the end target was not achieved, it made quantifiable progress almost at 100% (almostdoubled from the baseline).It should also be noted that when using the METT scores, progress is not Linear. | end target was set at mid-term only only in response to management demands, it was never part of the original M&E package for theproject in the PAD. Targets were overly |
INDICATOR | LÍNEA DE REFERENCIA | EN CURSO | OBJETIVO |
---|
75% of community development micro-projects funded by the Community Fund, FIAL, each year considered to have satisfactorialy achieved their objectives. | Valor | 0, as no micro-projects have been funded yet | 81.3% | 75% of micro-projects considered satisfactory. |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | Target overly achieved. |
Ecosystem health and function maintained or improved within protected areas, their buffer zones, the Biosphere Reserve and fishing reserves. | Valor | |||
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | ||
Comentar | This indicator will be monitored through the same measurements as PDO indicator 1, the PA and MPA tracking tool (see values forPDOindicator 1). |
Sector policies, procedures and regulations required for EIA prepared | Valor | Not prepared | Prepared | |
Fecha | 14 de marzo de 2005 | 28 de enero de 2011 | 31 de marzo de 2011 | |
Comentar | The Environmental Impact Assessment Law was approved by the Parliament in May 2010 and was promulgated and published in theofficial gazette in September 2010 |
Quality and timeliness of project implementation | Valor | |||
Fecha | 28 de enero de 2011 | 31 de marzo de 2011 | ||
Comentar | Project implementation is progressing well, indicators are close to their targets and Financial reports are delivered on time -there was a delay in submitting the audit report for 2009. |