Sustainable Management of Mineral Resources Project

Resumen*

The overall objective of the Sustainable Management of Mineral Resources Project, is to assist the Government of Uganda (GOU) implement its strategy to accelerate sustainable development, and reduce poverty by strengthening governance, transparency, and capacity in the management of mineral resources, with particular emphasis on community development in mining areas, and improve small-scale, and artisanal mining, in addition to promoting a socially...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

Strengthening Government's capacity to develop a sound minerals sector based on private investments and improvements in selected artisanal and small scale mining areas

Llave Detalles

Proyecto Detalles

  • P079925

  • Closed

  • Christopher Sheldon

  • N/A

  • Uganda

  • 29 de mayo de 2003

  • (a partir de la presentación ante el Directorio)

    9 de diciembre de 2003

  • 17 de agosto de 2004

  • US$ 25.00 millones

  • B

  • 17 de septiembre de 2013

  • 31 de diciembre de 2011

  • BANK APPROVED

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
IDA Credit 25.00
Borrower/Recipient 3.00

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF No Disponible
Compromiso de la AIF 25.00
Compromiso del BIRF + AIF 25.00
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 28.00

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de marzo de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Progress towards achievement of PDO Satisfactory 2011-12-26
Project Management Satisfactory 2011-12-26
Financial Management Moderately Satisfactory 2011-12-26
Counterpart Funding Satisfactory 2011-12-26
Monitoring and Evaluation Satisfactory 2011-12-26
Overall Implementation Progress (IP) Satisfactory 2011-12-26
Procurement Moderately Satisfactory 2011-12-26

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 11-30-2012
ResultadosModerately Satisfactory
Riesgo para los resultados de desarrolloSubstantial
Desempeño del BancoModerately Satisfactory
Desempeño del prestatarioModerately Satisfactory
Desempeño del GobiernoModerately Unsatisfactory
Organismo EjecutorModerately Satisfactory

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 06-27-2014INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO:
Calificación De Los ResultadosModerately Satisfactory N/a
Riesgo Para Los Resultados De DesarrolloHighN/a
Desempeño Del BancoModerately SatisfactoryN/a
Desempeño Del PrestatarioModerately SatisfactoryN/a
Desempeño Del GobiernoModerately UnsatisfactoryN/a
Organismo EjecutorModerately SatisfactoryN/a
Calidad Del IfeSatisfactoryN/a
Calidad De SyeModestN/a

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Accuracy/transparency of licensing measured by zero unresolved complaintsValorNo system to record complaintsComplaints Book available with the Commissioner foZero valid, unresolved complaints. 100% first come
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    ComentarInstallation of the Mining Cadastre System has commenced. A book for registration of complaints will be established and kept inthe DGSM Commissioner's Office.Achieved. The complaints mechanism will later be taken up by the electronic cadaster system.
  • Uganda achieves transparency of mining sector revenues as evidenced by regular publication of such revenues.ValorSector revenues not publishedSector Revenue Data at the local government level Publicly available sector revenue data.
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    ComentarThe Mining Act spells out that 20% of royalty collected from Mining Companies has to be given to the beneficiary districts (17%)and landowners (3%). This information is now advertised in the local newspapers since April 2009 to December 2010.Achieved.
  • Mineral exploration and development (US$m and number of exploration licenses).Valor$5 million; 190 licenses$346 mill, 607 licenses$30 million (cumulative)
    Fecha31 de diciembre de 200330 de septiembre de 201131 de diciembre de 2011
    Comentar2005 Baseline: US$ 40.65 millCumulative value since 2005. Jan-Sept 2011: $33.2Cumulative number of (active) exploration licenses from 2005 to end November2011is 607. 170 of these were granted newly in 2011. "Active" licenses include existing, renewed and newly issued licenses minusexpired licenses.Achieved
  • Fiscal revenues from mining (US$m, annually)Valor$0.55 million (UGX 1.1 billion)$3.08 million (UGX 8.03 billion) or increase of 60+50%
    Fecha31 de diciembre de 200330 de septiembre de 201131 de diciembre de 2011
    ComentarJan-Sept 2011 fiscal revenues were $ 3.08. This 2011 value includes payment of arrears by KCCL (accumulated outstanding royaltyfees of UGX 3,845,835,308 from 06/2004-12/2009.Achieved.
  • Number of licenses given to artisanal and small scale miners (ASM) .Valor100726300
    Fecha31 de diciembre de 200330 de septiembre de 201131 de diciembre de 2011
    Comentar100 licensesCumulative number of ASM licenses issued to end September 2011 is 726 of which 250 were granted newly in 2011. This includes allASM licenses issued (Prospecting, Exploration, Location, Retention, Mineral Dealers and Mining Leases)Achieved.
  • Incomes of formalized ASMValoraverage of $3 per dayaverage of $5 per day/ $ 7.5 per dayImprovement of 10%
    Fecha31 de diciembre de 200612 de diciembre de 201131 de diciembre de 2011
    ComentarNo baseline in 2003, baseline study undertaken in 2006.$5 per day for ASMs dealing in precious metals whose price is determined by international commodity prices; $7.5 day for ASMdealing in industrial minerals whose price is determined by the local market.This information will be updated with a beneficiarysurvey for the ICR.Achieved
  • Direct project beneficiariesValor0.002807.002807.00
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    ComentarIndicator added at last mission to demonstrate local level benefits.Additional Information. No target was set.
  • Female beneficiariesValor0.0045.0045.00
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    Comentar
  • People who were trained and/or partizipated in gender sensitization programs under the projectValor0.001000.001000.00
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    ComentarIn total one thousand (1000) people benefited from the trainings: 600 men and 400 women
  • Community members benefitting from the Small Grants ProgramValor0.001500.001500.00
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    ComentarOverall 18 Cooperatives/ Associations were supported with small grants.
  • People employed at construction site and in local communities who provided services during airborne surveyValor0.0088.0088.00
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    ComentarThe construction site employed on average 68 people; about 20 persons form local communities helped with services for the airbornesurvey (driving, cooking).
  • Mining Companies/ People who have purchased geological information or maps from the documentation centre supported under the projectValor0.0039.0039.00
    Fecha31 de diciembre de 200712 de diciembre de 201131 de diciembre de 2011
    ComentarSince 2007, 39 companies have bought geological information. Sales revenue from that amounted to UGX 132,413,590 (an equivalent ofUS$ 58,000 at current exchange rate). Some of the biggest investors in mining were among them, such as Anglo Gold Ashanti, RioTintoand other key players in the African mining sector such as African Minerals, MS Randgold Resources and AUC Mining.

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Review of mineral code and regulations and revisions as required.Valornot started.Review undertaken by Commonwealth SecretariatDone
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    ComentarCommonwealth Secretariat has completed the review and a copy has been provided to the Association.Achieved
  • Mining cadastre and registry system established.Valor0%60%100%
    Fecha31 de diciembre de 200312 de diciembre de 201130 de junio de 2011
    ComentarImplementation commenced in June 2011 and is steadily progressing. Funded by NDF.To be completed by June 2012.
  • Regional branches of DGSM operationalValor447
    Fecha31 de diciembre de 200331 de mayo de 201131 de diciembre de 2011
    Comentar4 branches operational4 branches operational. Insufficient funds for construction of 3 new Regional branches. Financing by IDA caters for construction&refurbishment of the buildings at DGSM HQs. The funds for the refurbishment of the existing 4 regional branches and constructionof the new 3 regional branches will be sought from Ministry of Finance Planning and Economic Development (MoFPED) under the FiveYearDevelopment Plan of National Planning Authority (NPA). Construction of buildings in DGSM HQs is in progress.Activity dropped. Not achieved; GoU agreed to fund under the Five Year Development Plan
  • Time to process prospecting and exploration licenses.Valor14No change4
    Fecha31 de diciembre de 200331 de mayo de 201130 de junio de 2011
    Comentar14 daysDesign of the Cadastre and Registry System, financed by NDF, has been completed. Implementation of the Cadastre & Registry Systemis in progress.Achieved for Prospecting Licensed.Well on track for Exploration Licenses.4 days, excluding 4 day period for applicant to pay fees.
  • Toolkit for baseline profiling of ASM communities in Uganda available.ValorNoneCompletedCompleted
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    ComentarToolkit is in place. ASM Handbook has been published (750 copies) and widely distributed, in particular under the Train theTrainer Modules as reference material.Achieved.
  • Number of cooperatives/miners organizations.Valor03250
    Fecha31 de diciembre de 200331 de marzo de 201130 de junio de 2011
    ComentarSome local ASM associations broke away to form joint ventures with mining companies and now have the exploration licenses. Whilethe number of miners organisations is lower than expected, to see ASMs forming JV's is a positive sign as it shows the progressionfrom artisanal to small-scale/medium scale producer.Achieved.
  • Number of ASMs with Health and safety plans (can be in EIA).Valor0796100
    Fecha31 de diciembre de 200331 de diciembre de 201031 de diciembre de 2011
    ComentarASMs are required to submit project briefs including health and safety plans under the new law. 2005 was the first reporting year.Cumulative number from 2005 to end Sept 2011.Achieved.
  • Number of gender consultations and training.ValorNone2520
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    Comentar5 major & 20 minor consultations with participation of 600 men and 400 women have been conducted and concluded.Achieved
  • Creation of a Social and Environment Unit (SEU), mainstreamed into DGSM.ValorNoYes
    Fecha31 de diciembre de 200331 de mayo de 201130 de junio de 2011
    ComentarSEU established & staff recruited to be mainstreamed in DGSM structure as in the design of the Institutional Model of DGSM.Institutional Review completed & Cabinet Paper is prepared by MEMD and will be tabled for ratification to Parliament andsubsequently submitted to the Ministry of Public Service for implementation.Achieved in principle, but may be sustainability at risk. SMMRP established an Environmental and Social Unit (SEU) under DGSM tomanage related issues in liaison with National Environment and Management authority (NEMA). Three (3) persons were recruited andtrained together with other geoscientists in various areas of environment and social issues. Equipment and tools for baselinestudies andmonitoring environment have been procured and the unit routinely carries out sensitization of miners and communities onenvironment,social, health and safety issues related to mining activities. The Ministry of Energy and Mineral Development hasproposed a structure that will mainstream the SEU under DGSM and a permanent staff member has been assigned as head of the SEU.However, by the end ofthe project the staff and activities of the unit that have been funded by the project will come to halt. TheMinistry of Public Service has to approve the budget in order to mainstream the SEU into the regular civil service. The requestwill be included in a petition to Parliament. If considered favorably, a Certificate of Payment can be issued by Cabinet to allowpayments by the Treasury. Thedecision is expected for January 2012.
  • Creation of computerized environmental management system.Valor0%90%100%
    Fecha31 de diciembre de 200312 de diciembre de 201031 de diciembre de 2011
    ComentarConsultancy for the activity is completed. The Environmental and Social Management Information System (ESMIS) is fully operationalin a temporary facility and will transferred to the new premises after construction and refurbishment of the buildings at DGSM HQs.Achieved.
  • Review of Environmental Impact Assessments for mining to assess quality/compliance with environmental requirements.Valor10%100%100%
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    Comentar10% of mining operations with EIA100% compliant for new operations requiring EIAs. 8 mining operations have undertaken a full EIA (100%) as required by law and alloperations whose license was issued under the old law have undergone an environmental audit (19), also as required by law. Aboutthree of those did not comply and are currently with suspended working obligations until compliance can be verified.Achieved.
  • Percent of country covered by geophysical air-borne surveys.Valor50% of Regional surveys; 1% of high resolution sur80%85% of high resolution surveys
    Fecha31 de diciembre de 20034 de octubre de 201030 de junio de 2011
    ComentarTarget output is fully achieved. 648,400 line km of magnetic & radiometric surveys (>100% planned activity) have been flown withhigh resolution & 22,709 line km of Electromagnetic surveys have been done (80% country landmass).Achieved. 85% was entered in error and was never corrected. Target is 80%.
  • Establishment of publicly available Geological and Mineral Information System.ValorNoAwaiting installation in new building.Yes
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    ComentarDraft GMIS design & geodata inventory for maps & mine plans completed. All published & unpublished maps scanned. All maps of1:100,000/50,000/250,000 digitized & capture of metadata completed. Geodata portal has been constructed. To be installed in Dec2011 following completion of renovations at DGSM.Achieved in principle.Awaiting opening of new premises. Expected by end Dec 2011.
  • Reduced time to provide geological data.Valor14Awaiting installation in new building.1
    Fecha31 de diciembre de 200312 de diciembre de 201131 de diciembre de 2011
    Comentar14 daysAwaiting completion of construction at DGSM.Geodata portal is fully operational and is hosted on a local server in the meantime.Achieved in principle.Awaiting opening of new premises. Expected by end Dec 2011.