Manila Third Sewerage Project

Resumen*

The Manila Third Sewerage Project aims to: (a) increase the coverage and effectiveness of sewerage service delivery in participating areas of Metro Manila through an integrated approach involving septage management, sewage management, and heightened consumer awareness of water pollution problems and their solutions; and, (b) establish the financial and technical viability of new approaches for sewage management in Metro Manila (MM). The project has...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

The development objectives of the Manila Third Sewerage Project are to: (a) increase the coverage and effectiveness of sewerage service delivery in participating areas of Metro Manila through an integrated approach involving septage management, sewage management,and heightened consumer awareness of water pollution problems and their solutions; and, (b) establish the financial and technical viability of new approaches for sewage management in MM.

Llave Detalles

Proyecto Detalles

  • P079661

  • Closed

  • Christopher Ancheta

  • N/A

  • Filipinas

  • 21 de noviembre de 2003

  • (a partir de la presentación ante el Directorio)

    21 de junio de 2005

  • 6 de marzo de 2006

  • US$ 64.00 millones

  • A

  • No aplicable

  • 30 de junio de 2012

  • BANK APPROVED

  • 15 de enero de 2013

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
Borrower/Recipient 20.46
International Bank for Reconstruction and Development 64.00

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF 64.00
Compromiso de la AIF No Disponible
Compromiso del BIRF + AIF 64.00
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 84.46

Resumen del financiamiento del Banco Mundial (millones de US$) al 31 de julio de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 31 de julio de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2012-08-07
Monitoring and Evaluation Moderately Unsatisfactory 2012-08-07
Financial Management Moderately Satisfactory 2012-08-07
Overall Implementation Progress (IP) Moderately Satisfactory 2012-08-07
Counterpart Funding Satisfactory 2012-08-07
Procurement Satisfactory 2012-08-07
Project Management Satisfactory 2012-08-07

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 12-27-2012
ResultadosModerately Satisfactory
Riesgo para los resultados de desarrolloModest
Desempeño del BancoModerately Satisfactory
Desempeño del prestatarioModerately Satisfactory
Desempeño del GobiernoModerately Satisfactory
Organismo EjecutorModerately Satisfactory

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 03-12-2015INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO:
Calificación De Los ResultadosUnsatisfactory N/a
Riesgo Para Los Resultados De DesarrolloModerateN/a
Desempeño Del BancoModerately UnsatisfactoryN/a
Desempeño Del PrestatarioModerately UnsatisfactoryN/a
Desempeño Del GobiernoModerately UnsatisfactoryN/a
Organismo EjecutorModerately UnsatisfactoryN/a
Calidad Del IfeUnsatisfactoryN/a
Calidad De SyeNegligibleN/a

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Increase in satisfaction of residents w/sewerage/sanitation service delivery in participating areas including health incidences of diarrhea.Valornone providedYesAnnual increases starting Yr 3 through Yr 6.
    Fecha21 de junio de 200531 de diciembre de 201130 de junio de 2012
    ComentarNo baseline data was provided in the PAD and Project Agreement. In Dec 2008, a 6% decline in diarrhea incidents per person wasrecorded.No value was indicated in the Results Framework Monitoring because there is no uniform metrics to measure the increase/decrease insatisfaction (e.g. not all respondents on survey are from the MTSP catchments. DOH figures on diarrhea are not confined within theEast Concession area only. (Have requested MWCI to justify in the ICR)No end target stated in the PAD and Project Agreement. Just indicate "Yes" if there is an increase starting year 3. If thesatisfaction rate of the residents increased, this translates to improved services including decreased incidences of diarrhea.
  • Total BOD removed by the project (tons/year).Valor5,600206,37220,400
    Fecha30 de junio de 200531 de diciembre de 201130 de junio de 2012
    ComentarThe baseline was based on the existing treatment plants prior to the project.The actual figure represents an overachievement by 900%. Comulative figures includes both septage and sewage treatment plantsunder an expanded service area of intercepted combined flows. (We are verifying this figure with MWCI to account for the hugeoverachievement and have requested to justify in the ICR.)The target for the original closing date in June 2010 is 20,400. This was not revised in the restructuring. (This target wasbasedon the assumption that the BOD volume removed is from the connected Households to the sewer network.)
  • Percent increase in take-up rate of desludging service (% take-up rate/yr).Valornone providedYesAnnually Yr 3 - Yr 6
    Fecha30 de junio de 200531 de diciembre de 201130 de junio de 2012
    ComentarNo baseline provided in the PAD and Project Agreement. Based on earlier data, the number of septic tanks desludged in MWCI areasincreased by 42% from 2005 to 2006.No quantification in PAD for this indicator, simply indicates yes or no if there is an increase. However, we can see this in thenumber of tanks desludged, which increased by 6% from 826,870 in 2010 to 879,017 in 2011.No target indicated in the PAD and Project Agreement.
  • Number of sewage treatment plants treating combined flows in a sustainable manner that comply with relevant discharge standards.Valor068
    Fecha30 de junio de 200531 de diciembre de 201130 de junio de 2012
    ComentarUnderachievement is due to cancellation of Taguig subprojects.Target was downgraded from 9 to 8 in the restructuring of the project. In the course of implementation, the original 8 was reducedto 7 as the Taguig subproject warranted an STP with a sewer network.
  • Cost of operation is in an acceptable range.Valor020%around 20%
    Fecha30 de junio de 200531 de diciembre de 201130 de junio de 2012
    ComentarThe cost of operation of the completed projects is within the range at no more than 20%.Target of 20% starts at year 3. Values are confidential. Hence, the target is only a range.

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Sewage management. Number of water connections in MWCI service area with sewage treatment service (cumulative # by end of yr).Valor46,350102,83549,500
    Fecha1 de enero de 200431 de diciembre de 201030 de junio de 2012
    ComentarThere was an overachievement of the target. Note however, the target was reduced during the restructuring of the project.Target was downgraded to 49,500 from 117,000 during the restructuring of the project
  • Volume of sewage treated before disposal (cum. 1000 m3/yr).Valor7,026111,345113,227
    Fecha1 de enero de 200431 de diciembre de 201030 de junio de 2012
    ComentarLatest actual figures are witihn reach of the target. It will reach its target by project close in June 2012.This figure is the original target for June 30, 2010. This was not revised in the restructuring.
  • Length of drainage lines installed/rehabilitated (cum. km by end of yr).Valor0021
    Fecha1 de enero de 200431 de diciembre de 201030 de junio de 2012
    ComentarIn the PAD, this was noted as subject to verification of surveyed length of drainage lines requiring rehabilitation.The figure is still to be discussed by MWCI. The drainage lines are the responsibility of the local government units, hence,passing on the CAPEX to the concessionaire would mean an increase in the tariff that will be passed on to the consumers. Thescaled down figure was included in areas where there is a necessity for the linkages of the conveyance of wastewater to the STP.One of the candidate sub-projects that may include such activity is the proposed Taguig sewer system.Target was scaled down to 21 from 120 during the restructuring to cater to the proposed Taguig sewer network. However, the Taguigsubproject was cancelled.
  • Septage Management.Number of septic tanks desludged in MWCI service area (cum. # by end of yr).Valor17,000826,870250,560
    Fecha1 de enero de 200431 de diciembre de 201030 de junio de 2012
    ComentarTarget was overachieved even surpassing the end of project target.
  • Volume of septage treated before disposal (cumulative m3 by end of yr).Valor01,008,740982,800
    Fecha1 de enero de 200431 de diciembre de 201030 de junio de 2012
    ComentarProject end target already achieved
  • Percentage of BOD reduction in the septic tanks in a sample not smaller than 0.5% year (%average reduction).Valoraround 10%20%around 20%
    Fecha1 de enero de 200431 de diciembre de 201030 de junio de 2012
    ComentarBaseline studies were done in 2008.20% is reached. No quantification in the PAD for this indicator.The 20% is the target at project end.
  • Institutional Strengthening.Number of people reached by public information campaign (% average reduction).Valor01,508,097957,090
    Fecha1 de enero de 200431 de diciembre de 201130 de junio de 2012
    ComentarIndicator already achieved the year-end target.
  • Percent increase in take-up rate of deslugding services (% take-up rate/yr.).Valor0YesYes
    Fecha1 de enero de 200431 de diciembre de 201130 de junio de 2012
    ComentarNo quantification in the PAD and Project Agreement. In Dec. 2008, the percent increase in take up rate of desludging services was14.5%.No quantification in PAD for this indicator, simply indicates yes or no if there is an increase. However, we can see this in thenumber of tanks desludged, which increased by 6% from 826,870 in 2010 to 879,017 in 2011.No quantification in the PAD and Project Agreement.
  • Prepared follow up wastewater and sanitation programs.Valor0YesFollow-up program(s) prepared
    Fecha1 de enero de 200431 de diciembre de 201130 de junio de 2011
    ComentarNo quantification in the PAD and Project Agreement.MWCI has already prepared FS for the Marikina river and has started implementation in three catchments already. A follow-up loan,the Metro Manila Wastewater Project has been approved by the Bank.No quantification in PAD and project Agreement.