Entidad De Financiamiento | Compromisos |
---|---|
Borrower/Recipient | 20.46 |
International Bank for Reconstruction and Development | 64.00 |
P079661
Closed
Christopher Ancheta
N/A
21 de noviembre de 2003
(a partir de la presentación ante el Directorio)
21 de junio de 2005
6 de marzo de 2006
US$ 84.46 millones
N/A
2005
US$ 64.00 millones
A
No aplicable
30 de junio de 2012
BANK APPROVED
15 de enero de 2013
Entidad De Financiamiento | Compromisos |
---|---|
Borrower/Recipient | 20.46 |
International Bank for Reconstruction and Development | 64.00 |
Línea de productos | BIRF/AIF |
---|---|
Compromiso del BIRF | 64.00 |
Compromiso de la AIF | No Disponible |
Compromiso del BIRF + AIF | 64.00 |
Instrumento de Financiamiento | |
---|---|
Monto a título de donación | No Disponible |
Costo total del proyecto** | 84.46 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Unsatisfactory | 2012-08-07 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2012-08-07 |
Financial Management | Moderately Satisfactory | 2012-08-07 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2012-08-07 |
Counterpart Funding | Satisfactory | 2012-08-07 |
Procurement | Satisfactory | 2012-08-07 |
Project Management | Satisfactory | 2012-08-07 |
INDICADOR | INFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 12-27-2012 |
---|---|
Resultados | Moderately Satisfactory |
Riesgo para los resultados de desarrollo | Modest |
Desempeño del Banco | Moderately Satisfactory |
Desempeño del prestatario | Moderately Satisfactory |
Desempeño del Gobierno | Moderately Satisfactory |
Organismo Ejecutor | Moderately Satisfactory |
INDICADOR | REVISIÓN DEL ICR: 03-12-2015 | INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO: |
---|---|---|
Calificación De Los Resultados | Unsatisfactory | N/a |
Riesgo Para Los Resultados De Desarrollo | Moderate | N/a |
Desempeño Del Banco | Moderately Unsatisfactory | N/a |
Desempeño Del Prestatario | Moderately Unsatisfactory | N/a |
Desempeño Del Gobierno | Moderately Unsatisfactory | N/a |
Organismo Ejecutor | Moderately Unsatisfactory | N/a |
Calidad Del Ife | Unsatisfactory | N/a |
Calidad De Sye | Negligible | N/a |
INDICATOR | LÍNEA DE REFERENCIA | EN CURSO | OBJETIVO |
---|
Increase in satisfaction of residents w/sewerage/sanitation service delivery in participating areas including health incidences of diarrhea. | Valor | none provided | Yes | Annual increases starting Yr 3 through Yr 6. |
Fecha | 21 de junio de 2005 | 31 de diciembre de 2011 | 30 de junio de 2012 | |
Comentar | No baseline data was provided in the PAD and Project Agreement. In Dec 2008, a 6% decline in diarrhea incidents per person wasrecorded. | No value was indicated in the Results Framework Monitoring because there is no uniform metrics to measure the increase/decrease insatisfaction (e.g. not all respondents on survey are from the MTSP catchments. DOH figures on diarrhea are not confined within theEast Concession area only. (Have requested MWCI to justify in the ICR) | No end target stated in the PAD and Project Agreement. Just indicate "Yes" if there is an increase starting year 3. If thesatisfaction rate of the residents increased, this translates to improved services including decreased incidences of diarrhea. |
Total BOD removed by the project (tons/year). | Valor | 5,600 | 206,372 | 20,400 |
Fecha | 30 de junio de 2005 | 31 de diciembre de 2011 | 30 de junio de 2012 | |
Comentar | The baseline was based on the existing treatment plants prior to the project. | The actual figure represents an overachievement by 900%. Comulative figures includes both septage and sewage treatment plantsunder an expanded service area of intercepted combined flows. (We are verifying this figure with MWCI to account for the hugeoverachievement and have requested to justify in the ICR.) | The target for the original closing date in June 2010 is 20,400. This was not revised in the restructuring. (This target wasbasedon the assumption that the BOD volume removed is from the connected Households to the sewer network.) |
Percent increase in take-up rate of desludging service (% take-up rate/yr). | Valor | none provided | Yes | Annually Yr 3 - Yr 6 |
Fecha | 30 de junio de 2005 | 31 de diciembre de 2011 | 30 de junio de 2012 | |
Comentar | No baseline provided in the PAD and Project Agreement. Based on earlier data, the number of septic tanks desludged in MWCI areasincreased by 42% from 2005 to 2006. | No quantification in PAD for this indicator, simply indicates yes or no if there is an increase. However, we can see this in thenumber of tanks desludged, which increased by 6% from 826,870 in 2010 to 879,017 in 2011. | No target indicated in the PAD and Project Agreement. |
Number of sewage treatment plants treating combined flows in a sustainable manner that comply with relevant discharge standards. | Valor | 0 | 6 | 8 |
Fecha | 30 de junio de 2005 | 31 de diciembre de 2011 | 30 de junio de 2012 | |
Comentar | Underachievement is due to cancellation of Taguig subprojects. | Target was downgraded from 9 to 8 in the restructuring of the project. In the course of implementation, the original 8 was reducedto 7 as the Taguig subproject warranted an STP with a sewer network. |
Cost of operation is in an acceptable range. | Valor | 0 | 20% | around 20% |
Fecha | 30 de junio de 2005 | 31 de diciembre de 2011 | 30 de junio de 2012 | |
Comentar | The cost of operation of the completed projects is within the range at no more than 20%. | Target of 20% starts at year 3. Values are confidential. Hence, the target is only a range. |
INDICATOR | LÍNEA DE REFERENCIA | EN CURSO | OBJETIVO |
---|
Sewage management. Number of water connections in MWCI service area with sewage treatment service (cumulative # by end of yr). | Valor | 46,350 | 102,835 | 49,500 |
Fecha | 1 de enero de 2004 | 31 de diciembre de 2010 | 30 de junio de 2012 | |
Comentar | There was an overachievement of the target. Note however, the target was reduced during the restructuring of the project. | Target was downgraded to 49,500 from 117,000 during the restructuring of the project |
Volume of sewage treated before disposal (cum. 1000 m3/yr). | Valor | 7,026 | 111,345 | 113,227 |
Fecha | 1 de enero de 2004 | 31 de diciembre de 2010 | 30 de junio de 2012 | |
Comentar | Latest actual figures are witihn reach of the target. It will reach its target by project close in June 2012. | This figure is the original target for June 30, 2010. This was not revised in the restructuring. |
Length of drainage lines installed/rehabilitated (cum. km by end of yr). | Valor | 0 | 0 | 21 |
Fecha | 1 de enero de 2004 | 31 de diciembre de 2010 | 30 de junio de 2012 | |
Comentar | In the PAD, this was noted as subject to verification of surveyed length of drainage lines requiring rehabilitation. | The figure is still to be discussed by MWCI. The drainage lines are the responsibility of the local government units, hence,passing on the CAPEX to the concessionaire would mean an increase in the tariff that will be passed on to the consumers. Thescaled down figure was included in areas where there is a necessity for the linkages of the conveyance of wastewater to the STP.One of the candidate sub-projects that may include such activity is the proposed Taguig sewer system. | Target was scaled down to 21 from 120 during the restructuring to cater to the proposed Taguig sewer network. However, the Taguigsubproject was cancelled. |
Septage Management.Number of septic tanks desludged in MWCI service area (cum. # by end of yr). | Valor | 17,000 | 826,870 | 250,560 |
Fecha | 1 de enero de 2004 | 31 de diciembre de 2010 | 30 de junio de 2012 | |
Comentar | Target was overachieved even surpassing the end of project target. |
Volume of septage treated before disposal (cumulative m3 by end of yr). | Valor | 0 | 1,008,740 | 982,800 |
Fecha | 1 de enero de 2004 | 31 de diciembre de 2010 | 30 de junio de 2012 | |
Comentar | Project end target already achieved |
Percentage of BOD reduction in the septic tanks in a sample not smaller than 0.5% year (%average reduction). | Valor | around 10% | 20% | around 20% |
Fecha | 1 de enero de 2004 | 31 de diciembre de 2010 | 30 de junio de 2012 | |
Comentar | Baseline studies were done in 2008. | 20% is reached. No quantification in the PAD for this indicator. | The 20% is the target at project end. |
Institutional Strengthening.Number of people reached by public information campaign (% average reduction). | Valor | 0 | 1,508,097 | 957,090 |
Fecha | 1 de enero de 2004 | 31 de diciembre de 2011 | 30 de junio de 2012 | |
Comentar | Indicator already achieved the year-end target. |
Percent increase in take-up rate of deslugding services (% take-up rate/yr.). | Valor | 0 | Yes | Yes |
Fecha | 1 de enero de 2004 | 31 de diciembre de 2011 | 30 de junio de 2012 | |
Comentar | No quantification in the PAD and Project Agreement. In Dec. 2008, the percent increase in take up rate of desludging services was14.5%. | No quantification in PAD for this indicator, simply indicates yes or no if there is an increase. However, we can see this in thenumber of tanks desludged, which increased by 6% from 826,870 in 2010 to 879,017 in 2011. | No quantification in the PAD and Project Agreement. |
Prepared follow up wastewater and sanitation programs. | Valor | 0 | Yes | Follow-up program(s) prepared |
Fecha | 1 de enero de 2004 | 31 de diciembre de 2011 | 30 de junio de 2011 | |
Comentar | No quantification in the PAD and Project Agreement. | MWCI has already prepared FS for the Marikina river and has started implementation in three catchments already. A follow-up loan,the Metro Manila Wastewater Project has been approved by the Bank. | No quantification in PAD and project Agreement. |