URBAN UPGRADING PROJECT

Resumen*

The objectives of the Vietnam Urban Upgrading Project are to alleviate poverty in urban areas by improving the living and environmental conditions of the urban poor using participatory planning methods, and influencing planning processes to become more inclusive and pro-poor. The project will be carried out in four cities-Ho Chi Minh City and Can Tho in the south, and Haiphong and Nam Dinh in the north. All four cities have numerous low-income, infrastructure-deficient...

* El resumen del proyecto es elaborado sobre la base del documento de evaluación inicial, el informe de evaluación inicial preparado por el personal o el documento del programa y es posible que no refleje exactamente la índole actual del proyecto.

Ver Más

Objetivo de desarrollo

To alleviate poverty in urban areas by improving the living and environmental conditions of the urban poor using participatory planning methods, and influencing planning processes to become more inclusive and pro-poor

Llave Detalles

Proyecto Detalles

  • P070197

  • Closed

  • Hoa Thi Hoang

  • N/A

  • Viet Nam

  • 22 de enero de 2002

  • (a partir de la presentación ante el Directorio)

    29 de abril de 2004

  • 6 de octubre de 2004

  • US$ 389.60 millones

  • Ministry of Construction,Nam Dinh City People's Committee,Can Tho City People's Committee,Hai Phong City People's Committee,Ho Chi Minh City People's Committee

  • Asia oriental y el Pacífico

  • 2004

  • US$ 389.60 millones

  • A

  • No aplicable

  • 31 de diciembre de 2014

  • BANK APPROVED

  • 12 de julio de 2023

  • Notes

Finanzas

Financiamiento (millones de US$)

No hay datos disponibles.
Entidad De Financiamiento Compromisos
International Bank for Reconstruction and Development 1.20
IDA Credit 388.40

Financiamiento total del proyecto (millones de US$)

Línea de productos BIRF/AIF
Compromiso del BIRF 1.20
Compromiso de la AIF 388.40
Compromiso del BIRF + AIF 389.60
Instrumento de Financiamiento
Monto a título de donación No Disponible
Costo total del proyecto** 389.60

Resumen del financiamiento del Banco Mundial (millones de US$) al 30 de abril de 2025

Exportar:
No hay datos disponibles.
Entidad De Financiamiento Fecha De Aprobación Fecha De Cierre Principal Desembolsado Reembolsos Intereses Y Cargos

Actividad financiera detallada al 30 de abril de 2025

Exportar:
No hay datos disponibles.
Período Entidad De Financiamiento Tipo De Transacción Monto (US$)

Footnotes

Ratings

CALIFICACIONES DE LA EJECUCIÓN

Name Review Date
Progress towards achievement of PDO Satisfactory 2014-12-29
Monitoring and Evaluation Satisfactory 2014-12-29
Overall Implementation Progress (IP) Moderately Satisfactory 2014-12-29
Counterpart Funding Satisfactory 2014-12-29
Project Management Moderately Satisfactory 2014-12-29
Procurement Satisfactory 2014-12-29
Financial Management Moderately Satisfactory 2014-12-29

CALIFICACIONES DE LA TERMINACIÓN

INDICADORINFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 12-17-2015
ResultadosModerately Satisfactory
Riesgo para los resultados de desarrolloModest
Desempeño del BancoModerately Satisfactory
Desempeño del prestatarioModerately Satisfactory
Desempeño del GobiernoSubstantial
Organismo EjecutorModerately Satisfactory

CALIFICACIONES DE EVALUACIONES INDEPENDIENTES

INDICADORREVISIÓN DEL ICR: 06-27-2016INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO:
Calificación De Los ResultadosModerately Satisfactory N/a
Riesgo Para Los Resultados De DesarrolloModestN/a
Desempeño Del BancoModerately SatisfactoryN/a
Desempeño Del PrestatarioModerately SatisfactoryN/a
Desempeño Del GobiernoModerately SatisfactoryN/a
Organismo EjecutorModerately SatisfactoryN/a
Calidad Del IfeModestN/a
Calidad De SyeSubstantialN/a

Marco de resultados

INDICADORES DE OBJETIVOS DE DESARROLLO DE PROYECTOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • Improved service coverage (water, sanitation, sewerage, electricity, public lighting)Valor30-40% in project areas (water and sanitation)550,106 households (est. 2,718,967 people) with im865,623 people in 4 towns
    Fecha30 de abril de 200419 de diciembre de 201431 de diciembre de 2014
    Comentar
  • Reduced floodingValor0313.6 km of tertiary drainage in low income areas150 kms of drainage in low-income areas
    Fecha6 de octubre de 200419 de diciembre de 201431 de diciembre de 2014
    Comentar
  • Change in property valuesValor050 - 400%100%
    Fecha6 de octubre de 200419 de diciembre de 201431 de diciembre de 2014
    Comentar
  • Reduction in time and cost of acquiring land use certificatesValor60 daysless than 30 days, according to the Independent Im45 days
    Fecha26 de octubre de 200619 de diciembre de 201431 de diciembre de 2014
    Comentar
  • Operational sustainability of participating microcredit lending institutionsValorRepayment rate is high (between 93-100%) and finan
    Fecha19 de diciembre de 2014
    Comentar
  • Number of Households in areas with BOLUCsValortbdPMU estimated the rate to be between 74-91%.Final target was never established.
    Fecha6 de octubre de 200431 de diciembre de 201431 de diciembre de 2014
    Comentar

INDICADORES DE RESULTADOS INTERMEDIOS

INDICATORLÍNEA DE REFERENCIAEN CURSOOBJETIVO
  • # of new household water, sewer and electricity connectionsValor029,687 households with improved water connections18,200 (excluding Nam Dinh)
    Fecha30 de octubre de 200419 de diciembre de 201431 de diciembre de 2014
    Comentar
  • # of kms of tertiary drainage and road constructed or rehabilitatedValor0298 km of tertiary drainage and 340.7 km of tertia150 km of drainage in low-income areas
    Fecha30 de octubre de 200419 de diciembre de 201431 de diciembre de 2014
    Comentar
  • # of kms of primary and secondary roads, sewer/drainage, canal, lake, and bridges constructed new or improvedValor0243.5km road; 233km sewer/drainage; 28km canal; 7.150 km
    Fecha26 de octubre de 200419 de diciembre de 201431 de diciembre de 2014
    Comentar
  • # of serviced plots and/or low-cost housing units provided to low-income householdsValor01,962/2,641 constructed plots of land and 747/2,382,627
    Fecha26 de octubre de 200419 de diciembre de 201431 de diciembre de 2014
    Comentar
  • # of houses improved through housing improvement loansValor051,109 loans for housing improvement; and 43,751 l29,274 low-income households receiving loans
    Fecha30 de octubre de 200419 de diciembre de 201431 de diciembre de 2014
    Comentar
  • Repayment rate of micro loansValor100%93 - 100%95%
    Fecha26 de octubre de 200419 de diciembre de 201431 de diciembre de 2014
    Comentar
  • Clear strategy and 5-year investment plan for National Urban Upgrading ProgramValorNoneStrategy of NUUP approved by the Prime Minister: DFinal Strategy and investment plan available
    Fecha30 de octubre de 20048 de junio de 200931 de diciembre de 2012
    Comentar