Entidad De Financiamiento | Compromisos |
---|---|
IDA Credit | 32.60 |
Borrower/Recipient | 5.83 |
Local Communities | 0.07 |
Nordic Development Fund (NDF) | 6.80 |
P056018
Closed
Enrique Pantoja
N/A
11 de enero de 2001
(a partir de la presentación ante el Directorio)
18 de junio de 2002
25 de febrero de 2003
US$ 45.30 millones
N/A
2002
US$ 39.40 millones
B
18 de noviembre de 2013
30 de abril de 2013
BANK APPROVED
Entidad De Financiamiento | Compromisos |
---|---|
IDA Credit | 32.60 |
Borrower/Recipient | 5.83 |
Local Communities | 0.07 |
Nordic Development Fund (NDF) | 6.80 |
Línea de productos | BIRF/AIF |
---|---|
Compromiso del BIRF | No Disponible |
Compromiso de la AIF | 32.60 |
Compromiso del BIRF + AIF | 32.60 |
Instrumento de Financiamiento | |
---|---|
Monto a título de donación | 6.80 |
Costo total del proyecto** | 45.30 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2013-05-17 |
Overall Safeguards Rating | Satisfactory | 2013-05-17 |
Progress towards achievement of PDO | Satisfactory | 2013-05-17 |
Procurement | Satisfactory | 2013-05-17 |
Financial Management | Moderately Satisfactory | 2013-05-17 |
Monitoring and Evaluation | Satisfactory | 2013-05-17 |
Overall Safeguards Rating | Satisfactory | 2013-05-17 |
Counterpart Funding | Satisfactory | 2013-05-17 |
Project Management | Satisfactory | 2013-05-17 |
INDICADOR | INFORME DE LA TERMINACIÓN DE LA EJECUCIÓN Y DE RESULTADOS: 10-21-2013 |
---|---|
Resultados | Substantial |
Riesgo para los resultados de desarrollo | Modest |
Desempeño del Banco | Moderately Satisfactory |
Desempeño del prestatario | Substantial |
Desempeño del Gobierno | Substantial |
Organismo Ejecutor | Substantial |
INDICADOR | REVISIÓN DEL ICR: 06-09-2015 | INFORME DE LA EVALUACIÓN DEL DESEMPEÑO DEL PROYECTO: |
---|---|---|
Calificación De Los Resultados | Satisfactory | N/a |
Riesgo Para Los Resultados De Desarrollo | Moderate | N/a |
Desempeño Del Banco | Moderately Satisfactory | N/a |
Desempeño Del Prestatario | Satisfactory | N/a |
Desempeño Del Gobierno | Satisfactory | N/a |
Organismo Ejecutor | Satisfactory | N/a |
Calidad Del Ife | Satisfactory | N/a |
Calidad De Sye | Modest | N/a |
INDICATOR | LÍNEA DE REFERENCIA | EN CURSO | OBJETIVO |
---|
Key legal and procedural reforms have been approved, that permit to carry out massive national regularization program by the end ofthe project. | Valor | 0% | 100% | 100% |
Fecha | 1 de enero de 2002 | 15 de abril de 2013 | 30 de abril de 2010 | |
Comentar | No Indigenous Land Titling Law; Registry Law did not allow SIICAR; legal difficulties for regularization. | The Project supported the approval of: Law for Titling of Indigenous Peoples' Lands (2002); Cadastre Law (2004); andPublicRegistryLaw (2009) | Target achieved under original Credit |
At least 30% reduction in the average number of days to regularize property rights through the Property Intendancy in the pilot area. | Valor | Unknown | 25% | 30% |
Fecha | 15 de abril de 2013 | 30 de abril de 2013 | ||
Comentar | Figure based on preliminary findings from ongoing final project evaluation. Data analysis is currently being finalized and it willbe included in the ICR. |
At least 40% of the territory under irregular land tenure status (i.e. reformed sector, national and state land) in the pilot area has legal certainty about tenure. | Valor | 0 % of the pilot area was regularized | 35% | 40% |
Fecha | 25 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Based on preliminary findings from ongoing final project evaluation. Final figure to be confirmed. |
At least 70 % of beneficiaries receiving new rural titles fall under the category of "very small producer". | Valor | 85% | 70% | |
Fecha | 15 de abril de 2013 | 30 de abril de 2013 | ||
Comentar | New indicator under the AF | An estimate based on the draft evaluation report. Final figure to be confirmed. |
At least 40% of new titles are provided directly to women and/or jointly with their spouse/partner. | Valor | 51% | 40% | |
Fecha | 25 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | New indicator under the AF | An estimate based on the draft evaluation report. Final figure to be confirmed. |
At least 50% reduction in number of days required to register a transaction in SIICAR, in the pilot area. | Valor | 0% | 50% | 50% |
Fecha | 25 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | No system existed at the moment of Project appraisal | SIICAR has been made operational recently in Chinandega. In all other areas there is a reduction of at least 50% in the number ofdays required to register a transaction. Final figure to be confirmed. |
Public Registries in the pilot area are financially sustainable. | Valor | 100% | 100% | |
Fecha | 15 de abril de 2013 | 30 de abril de 2013 | ||
Comentar | The evaluation report confirmed that the Public Registries in the pilot area are financially sustainable. The final data analysisis being conducted as part of the final evaluation report. |
Land taxation rates updated in 33 municipalities in the pilot area through the use of cadastral survey information in SISCAT. | Valor | 30 | 33 | |
Fecha | 15 de abril de 2013 | 30 de abril de 2013 | ||
Comentar | New indicator under the AF | Databases transfered to 30 municipalities including information of over 300,000 parcels. Final figure to be confirmed. |
All protected areas under the Project are included in INETER's geographical database. | Valor | 0 | 17 | 14 |
Fecha | 25 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | PAs were not demarcated or geo-referenced | Surpassed (121%). | Target achieved. |
Indigenous Peoples' rights are enforced in 15 territories and respected by government authorities, and the national regional and municipal levels. | Valor | 0 | 15 | 15 |
Fecha | 25 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Territories were not demarcated or titled | Activities completed under the original Credit. | Target achieved |
INDICATOR | LÍNEA DE REFERENCIA | EN CURSO | OBJETIVO |
---|
Land policy framework prepared and consulted with key land administration actors. | Valor | Land Policy framewoek document did not exist | Land Policy Framework Document endorsed and in use | |
Fecha | 25 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2010 | |
Comentar | Policy Framework advanced through a consultation process. | Activity completed |
Organizational Development Plans designed, approved, and implemented. | Valor | ODPs fully implemented | ||
Fecha | 15 de abril de 2013 | 30 de abril de 2010 | ||
Comentar | Diagnostic established in 2001. | Target achieved under original Credit. | Activity completed |
UTOs established and maintaining close coordination in municipalities where surveying has been completed. | Valor | UTOs did not exist before the Project | UTOs operating in Project area | |
Fecha | 1 de enero de 2010 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Three UTOs integrated into regional offices of relevant agencies under the AF (in Chinandega, Esteli and Madriz). |
INETER has opened departmental offices where lacking in the Project area. | Valor | No Cadastre Office (INETER) in Madriz. | Offices operating | |
Fecha | 1 de enero de 2010 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | INETER offices operating in Project area, including Madriz. |
Cadastral surveying database transferred to at least 33 municipalities in the pilot area; and in 4 municipalities SIICAR and SISCATshare data as well as resources and technology for their management. | Valor | 0 | 30 | 33 |
Fecha | 1 de enero de 2010 | 15 de diciembre de 2012 | 30 de abril de 2013 | |
Comentar | New indicator under the AF |
Diagnostics to identify land tenure status on ejido and municipal lands have been carried out in at least 33 municipalities, to support titling processes. | Valor | 0 | 22 | 33 |
Fecha | 1 de enero de 2010 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | New indicator under the AF | There are 22 diagnostics on land tenure status by INIFOM. |
At least 52,282 rural and urban parcels regularized in the pilot area. | Valor | 0 | 32,677 | 52,282 |
Fecha | 1 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Measurement corrected. 62.5% actually achieved thus far.32,677parcels regularized: 20,197 rural titles; 12,480 urban titles. |
At least 12,600 of regularized parcels in the pilot area receive new titles. | Valor | 0 | 32,677 | 12,600 |
Fecha | 1 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Target surpassed (255%). 32,677 titles; 20,197 rural and 12,480 urban. |
At least 14,230 pending urban titles resolved. | Valor | 0 | 15525 | 14,230 |
Fecha | 1 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Target surpassed. 15525 urban titles received (109%). |
At least 15,554 rural titles provided. | Valor | 0 | 13488 | 15,554 |
Fecha | 1 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Over 86% of target achieved. |
At least 10,565 agrarian titles reviewed. | Valor | 0 | 32905 | 10,565 |
Fecha | 1 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Target surpassed (311%). |
At least 4,985 cases resolved by OCI, along with the provision of compensation resolutions. | Valor | 0 | 5563 | 4,985 |
Fecha | 1 de febrero de 2003 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Target surpassed (112%). |
At least 450 trained community mediators. | Valor | 0 | 342 | 450 |
Fecha | 1 de enero de 2010 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | 76% of target met. |
At least 2,225 detected boundary conflicts mediated. | Valor | 0 | 1622 | 2,225 |
Fecha | 1 de enero de 2010 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Out of 2,667 cases, 1,622 have been mediated. Out of these, 912 have reached an agreement. |
At least 14 protected areas under the Project demarcated. | Valor | 0 | 14 | 14 |
Fecha | 1 de enero de 2010 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Target met. | Activity completed |
At least 7 management plans prepared and implemented. | Valor | 0 | 8 (5) | 7 (5) |
Fecha | 1 de enero de 2010 | 15 de abril de 2013 | 30 de abril de 2010 | |
Comentar | Target surpassed in the case of preparation of management plans. | Activity completed |
At least 15 indigenous territories demarcated. | Valor | 0 | 15 | 15 |
Fecha | 1 de enero de 2010 | 15 de abril de 2013 | 30 de abril de 2010 | |
Comentar | Target achieved under the original Credit. | Activity completed |
At least 5 of titled territories have a productive subproject under implementation. | Valor | 0 | 3 | 5 |
Fecha | 1 de enero de 2010 | 15 de abril de 2013 | 30 de abril de 2010 | |
Comentar | Activity completed |
SIICAR linking the legal and geographic information on each property is fully operational in 4 pilot departments. | Valor | 0 | 1 | 4 |
Fecha | 1 de enero de 2010 | 15 de diciembre de 2012 | 30 de abril de 2013 | |
Comentar | SIICAR is operational in Chinandega. Estelí 12% of progress, León and Madriz have 6% of progress. |
At least 80% of regular properties included in SIICAR CAT are transferred to SIICAR REG. | Valor | 0% | 10990 | 80% |
Fecha | 1 de enero de 2010 | 15 de abril de 2013 | 30 de abril de 2013 | |
Comentar | Measurement corrected. 10,990 properties transfered thus far. |
SIIPRO contains updated information of the regularization cases submitted to the IP central level. | Valor | 100% | 100% | |
Fecha | 15 de abril de 2013 | 30 de abril de 2013 | ||
Comentar | New indicator under the AF | SIIPRO functioning in IP. |